6534 N LAUREL CANYON BLVD 91606
Certificate Information: 6534 N LAUREL CANYON BLVD 91606
- Application / Permit
- 22010-10000-04475
- Plan Check / Job No.
- B22LA17827
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Coffee Shop
- Work Description
- New 60'x23' drive through coffee shop. Core and shell only, TI under separte permit.
- Permit Issued
- Issued on 2/10/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | LAMAR DAVIS |
| Corrections Issued | 9/27/2022 | LAMAR DAVIS |
| Quality Review Completed | 10/5/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 10/7/2022 | APPLICANT |
| Applicant returned to address corrections | 11/10/2022 | LAMAR DAVIS |
| Disabled Access Plans Picked Up | 11/18/2022 | APPLICANT |
| Applicant returned to address corrections | 1/13/2023 | TU HUA |
| Plan Check Approved | 2/10/2023 | TU HUA |
| Issued | 2/10/2023 | APPLICANT |
| CofO in Progress | 2/21/2024 | JOHN KITCKO |
| Permit Finaled | 3/12/2024 | RICKEY JACKSON |
| CofO Issued | 3/12/2024 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2022 | ROMAN GUTIERREZ |
| Miscellaneous | Cleared | 11/2/2022 | LOUIS ORTEGA |
| Sewer availability | Cleared | 11/2/2022 | ROMAN GUTIERREZ |
| Historic Resource Verification | Cleared | 11/10/2022 | MAX LODER |
| Highway dedication | Cleared | 11/18/2022 | ROMAN GUTIERREZ |
| Drive Through | Cleared | 11/23/2022 | COLLINS ALLAN |
| Redevelopment Project Area | Cleared | 11/28/2022 | DAVID URITA |
| Green Code | Cleared | 11/29/2022 | AARON COSTA |
| Hydrant and Access approval | Cleared | 12/2/2022 | KURT CORRAL |
| Miscellaneous | Cleared | 12/2/2022 | LAMAR DAVIS |
| Low Impact Development | Cleared | 1/24/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 1/27/2023 | JOHN LIN |
| ZA Case | Cleared | 2/2/2023 | JASON CHAN |
| DAS Clearance | Cleared | 2/9/2023 | EDDIE GARIN |
| Food establishment approval | Cleared | 2/10/2023 | LACDHS APPROVED |
Contact Information
| Architect | Rabbitt,, Jeffrey Allen; Lic. No.: C28914 | 933 W VALENCIA MESA DR. FULLERTON, CA 92835 |
| Contractor | Jasco Enterprise Inc; Lic. No.: 871467-B | 12439 MAGNOLIA BL 185 VALLEY VILLAGE, CA 91607 |
| Engineer | Nagarajan,, Sivaram; Lic. No.: S6349 | 167 MATISSE CIRCLE ALISO VIEJO, CA 92656 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/5/2023 | No Access for Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 7/5/2023 | No Access for Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 7/6/2023 | Corrections Issued | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 7/7/2023 | Approved | ROBERT DAVIS |
| Deputy Reinf. Concrete | 7/10/2023 | Conditional Approval | JOHN KITCKO |
| Deputy Steel/Welding | 8/30/2023 | Approved | JOHN KITCKO |
| Deputy Wood Construction | 9/14/2023 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 9/15/2023 | Not Ready for Inspection | JOHN KITCKO |
| Verify Sprinkler Sign Off | 9/15/2023 | Approved | JOHN KITCKO |
| Wood Frame | 9/15/2023 | Not Ready for Inspection | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Not Ready for Inspection | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | JOHN KITCKO |
| Wood Frame | 9/22/2023 | Not Ready for Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | Corrections Issued | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 10/26/2023 | Corrections Issued | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 10/30/2023 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 11/21/2023 | Approved | JOHN KITCKO |
| Interior/Exterior Lathing | 11/22/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Rough | 11/27/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 11/27/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Conditional Approval | JOHN KITCKO |
| Insulation | 11/30/2023 | Approved | JOHN KITCKO |
| Drywall Nailing | 12/1/2023 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Rough | 12/1/2023 | Not Ready for Inspection | JOHN KITCKO |
| Drywall Nailing | 12/4/2023 | Partial Inspection | JEFFREY FULTON |
| Special/Order Compliance | 12/13/2023 | Partial Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 12/26/2023 | Partial Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 12/28/2023 | Not Ready for Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 12/29/2023 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 1/5/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 1/12/2024 | Conditional Approval | JEFFREY DURAN |
| Drywall Nailing | 1/23/2024 | Approved | JOHN KITCKO |
| Final | 1/23/2024 | Corrections Issued | JOHN KITCKO |
| Footing/Foundation/Slab | 1/23/2024 | Approved | JOHN KITCKO |
| Green Building Final | 1/23/2024 | Approved | JOHN KITCKO |
| Green Building Rough | 1/23/2024 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 1/23/2024 | Approved | JOHN KITCKO |
| Wood Frame | 1/23/2024 | Approved | JOHN KITCKO |
| Final | 2/20/2024 | OK to Issue CofO | JOHN KITCKO |