3213 W 79TH ST 90043
Certificate Information: 3213 W 79TH ST 90043
- Application / Permit
- 22010-10000-04460
- Plan Check / Job No.
- B22LA17796
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN ADDITION TO GARAGE AND CONVERT TO ADU. PER LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 8/23/2023
- Issuing Office
- Current Status
- CofO Issued on 11/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2022 | SHANGQIN XIE |
| Corrections Issued | 9/14/2022 | KHUONG TRUONG |
| Plan Check Approved | 11/30/2022 | JOSEPH RAFOLS |
| Issued | 8/23/2023 | APPLICANT |
| CofO in Progress | 1/17/2024 | STUART CHAPMAN |
| Permit Finaled | 11/10/2024 | DEROLD HAUFF |
| CofO Issued | 11/10/2024 | DEROLD HAUFF |
| Permit Finaled | 11/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 9/30/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 11/17/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Ease-Build Inc; Lic. No.: 1087958-B | 5339 NEWCASTLE AVE #104 ENCINO, CA 91316 |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 2320 SANTA CRUZ CT TORRANCE, CA 90501 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/3/2023 | Corrections Issued | ANTHONY EGSON |
| METHANE-Barrier | 10/3/2023 | Approved | ANTHONY EGSON |
| METHANE-Subgrade | 10/3/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/3/2023 | Partial Approval | ANTHONY EGSON |
| Sewer | 10/3/2023 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 10/6/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/6/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/15/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 11/15/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/15/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 11/15/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/15/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 11/21/2023 | Approved | ENRIQUE MIRELES |
| Shower Pan | 11/21/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 12/11/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/11/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/3/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/3/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/3/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 1/16/2024 | Approved | STUART CHAPMAN |
| Final | 1/16/2024 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 1/16/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 1/16/2024 | Approved | STUART CHAPMAN |