1512 W 98TH ST 90047
Certificate Information: 1512 W 98TH ST 90047
- Application / Permit
- 22010-10000-04456
- Plan Check / Job No.
- B22LA17782
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Addition of 21x 23 Accessory Dwelling Unit (ADU) to (E) garage per State Law
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2022 | MINA HABILI |
| Corrections Issued | 9/15/2022 | MINA HABILI |
| Applicant returned to address corrections | 10/12/2022 | MINA HABILI |
| Applicant returned to address corrections | 1/17/2023 | MINA HABILI |
| Applicant returned to address corrections | 3/14/2023 | MINA HABILI |
| Plan Check Approved | 3/16/2023 | MINA HABILI |
| No Progress | 4/4/2023 | MINA HABILI |
| Plan Check Approved | 4/4/2023 | MINA HABILI |
| No Progress | 6/2/2023 | MINA HABILI |
| Plan Check Approved | 6/2/2023 | MINA HABILI |
| Plan Check Approved | 6/22/2023 | MINA HABILI |
| Plan Check Approved | 6/27/2023 | MINA HABILI |
| Issued | 6/27/2023 | APPLICANT |
| CofO in Progress | 9/20/2024 | AMIR NAZARIAN |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
| CofO Issued | 9/25/2024 | RUBEN SALAS |
| Permit Finaled | 9/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/20/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 10/11/2022 | STEVE MELGAR |
| Construction within easement | Cleared | 1/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Solomon'S Temple; Lic. No.: 668804-B | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: NA5524 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/18/2023 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/21/2023 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 7/25/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/27/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 7/27/2023 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 7/27/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/13/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/13/2023 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/18/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/18/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 1/31/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/31/2024 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 2/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/26/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/1/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 3/26/2024 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 3/26/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 3/26/2024 | Approved | JOSE MACIAS |
| Insulation | 4/15/2024 | Corrections Issued | JOSE MACIAS |
| Insulation | 4/26/2024 | Corrections Issued | JOSE MACIAS |
| Insulation | 5/10/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 5/22/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 7/23/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 7/23/2024 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/23/2024 | SGSOV Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | JOSE MACIAS |
| Final | 8/2/2024 | Corrections Issued | JOSE MACIAS |
| Gas Test | 8/2/2024 | Approved | JOSE MACIAS |
| Green Building Final | 8/2/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 8/2/2024 | Approved | JOSE MACIAS |
| METHANE-Final | 8/2/2024 | Approved | JOSE MACIAS |
| METHANE-Rough | 8/2/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 8/2/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 8/2/2024 | Approved | JOSE MACIAS |
| Final | 9/3/2024 | Conditional Approval | AMIR NAZARIAN |
| Final | 9/6/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 9/18/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 9/19/2024 | OK to Issue CofO | AMIR NAZARIAN |
| Pre-Inspection | 9/19/2024 | Approved | AMIR NAZARIAN |