6340-6340 1/2 S 11TH AVE 90043
Certificate Information: 6340-6340 1/2 S 11TH AVE 90043
- Application / Permit
- 22010-10000-04454
- Plan Check / Job No.
- B22LA17249
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2- STORY DUPLEX W/ ATTACHED 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/26/2023
- Issuing Office
- Current Status
- CofO Issued on 4/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | RAPHAEL ROSAS |
| Corrections Issued | 9/4/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 9/9/2022 | STEVEN KIM |
| Applicant returned to address corrections | 11/10/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/7/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 12/19/2022 | RAPHAEL ROSAS |
| No Progress | 3/15/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 4/10/2023 | RAPHAEL ROSAS |
| Issued | 7/26/2023 | APPLICANT |
| CofO in Progress | 3/29/2024 | JOSE MACIAS |
| Permit Finaled | 4/24/2024 | DEROLD HAUFF |
| CofO Issued | 4/24/2024 | DEROLD HAUFF |
| Permit Finaled | 4/24/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2022 | JEANETTE VONG |
| Highway dedication | Cleared | 9/17/2022 | JEANETTE VONG |
| Permit | Cleared | 9/17/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 9/19/2022 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 10/7/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 10/12/2022 | MITESH PATEL |
| Trees in Parkway | Cleared | 10/12/2022 | ADALBERTO VERA |
| Roof/Waste drainage to street | Cleared | 10/14/2022 | JEANETTE VONG |
| SB8 RUD | Cleared | 10/24/2022 | KENNETH LE |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/25/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 10/2/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/2/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 12/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/4/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 12/14/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/14/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/15/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/15/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/15/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 12/15/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/19/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 12/19/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 12/22/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/4/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/4/2024 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 1/29/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/22/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Final | 3/22/2024 | Approved | JOSE MACIAS |
| Final | 3/22/2024 | OK to Issue CofO | JOSE MACIAS |
| Green Building Final | 3/22/2024 | Approved | JOSE MACIAS |
| HVAC-Final | 3/22/2024 | Approved | JOSE MACIAS |
| PLUMBING-Final | 3/22/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Approved | JOSE MACIAS |
| Service/Power Release | 3/22/2024 | Approved | JOSE MACIAS |
| Smoke Detectors | 3/22/2024 | Approved | JOSE MACIAS |