2018 S THURMAN AVE 90016

Certificate Information: 2018 S THURMAN AVE 90016

Application / Permit
22010-10000-04445
Plan Check / Job No.
B22LA17737
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'-0" X 23' -6" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) - ALL WORK PER WFPP
Permit Issued
Issued on 2/17/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2022 APPLICANT
Assigned to Plan Check Engineer 9/13/2022 DANIEL ABRAMYAN
Corrections Issued 9/14/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 12/12/2022 VICTOR CHEN
Plan Check Approved 1/18/2023 WEIJIAN HUANG
Issued 2/17/2023 APPLICANT
CofO in Progress 3/4/2024 STUART CHAPMAN
Permit Finaled 3/13/2024 DEROLD HAUFF
CofO Issued 3/13/2024 DEROLD HAUFF
Permit Finaled 3/13/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/29/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 11/29/2022 JEANIE LAM
Sewer availability Cleared 12/5/2022 JEANIE LAM
Construction near power lines Cleared 12/12/2022 OSCAR CASTRO
Construction within easement Cleared 12/12/2022 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 12/12/2022 JEANIE LAM

Contact Information

Contractor James Terry R; Lic. No.: 572426-B 6226 ACACIA ST      LOS ANGELES, CA 90056

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/28/2023 Approved JOSE AVILA
Footing/Foundation/Slab 4/10/2023 Approved STUART CHAPMAN
ELECTRICAL-Rough 5/1/2023 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Approved JOSE AVILA
HVAC-Rough 5/1/2023 Partial Approval JOSE AVILA
PLUMBING-Rough 5/1/2023 Approved JOSE AVILA
Interior/Exterior Lathing 5/4/2023 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/5/2023 Approved JOSE AVILA
Shower Pan 5/5/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 5/25/2023 Partial Approval JOSE AVILA
Insulation 5/25/2023 Corrections Issued JOSE AVILA
Drywall Nailing 6/2/2023 Approved JOSE AVILA
Insulation 6/2/2023 Approved JOSE AVILA
Underground Mechanical 7/3/2023 Corrections Issued JOSE AVILA
Underground Mechanical 7/25/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/1/2023 Partial Inspection JOSE AVILA
Final 8/1/2023 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/1/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 8/1/2023 Approved JOSE AVILA
Verify Sprinkler Sign Off 8/1/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 2/29/2024 Approved STUART CHAPMAN
ELECTRICAL-Final 2/29/2024 Approved STUART CHAPMAN
ELECTRICAL-Rough 2/29/2024 Approved STUART CHAPMAN
Final 2/29/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 2/29/2024 Approved STUART CHAPMAN
HVAC-Rough 2/29/2024 Approved STUART CHAPMAN
PLUMBING-Final 2/29/2024 Approved STUART CHAPMAN
Service/Power Release 2/29/2024 Approved STUART CHAPMAN
Service/Power Release 3/13/2024 Approved STUART CHAPMAN