153 E 87TH ST 90003
Certificate Information: 153 E 87TH ST 90003
- Application / Permit
- 22010-10000-04422
- Plan Check / Job No.
- B22LA17083
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: SINGLE FAMILY DWELLING W/ ATTACHED 1-CAR GARAGE ($200,000)
- Permit Issued
- Issued on 4/18/2023
- Issuing Office
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | JAD BASMA |
| Quality Review Completed | 9/9/2022 | GARO TELMI |
| Plan Check Approved | 12/8/2022 | JAD BASMA |
| Applicant returned to address corrections | 12/9/2022 | JAD BASMA |
| Plan Check Approved | 4/10/2023 | JAD BASMA |
| Issued | 4/18/2023 | APPLICANT |
| CofO in Progress | 10/20/2023 | MICHAEL LEWIS |
| Permit Finaled | 10/23/2023 | DEROLD HAUFF |
| CofO Issued | 10/23/2023 | DEROLD HAUFF |
| Permit Finaled | 10/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/13/2022 | RYAN LY |
| Frnt yard landscape/Water mgmt | Cleared | 9/13/2022 | RYAN LY |
| Address approval | Cleared | 9/17/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 10/7/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 10/7/2022 | CHRIS VONG |
| Sewer availability | Cleared | 10/12/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/17/2022 | STEVE MELGAR |
| SB8 RUD | Cleared | 11/30/2022 | DORIS KWOK |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | , |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/16/2023 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/19/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 5/31/2023 | Partial Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 7/18/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 7/18/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/20/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/20/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 7/20/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 7/20/2023 | Approved | MICHAEL LEWIS |
| Insulation | 7/24/2023 | Approved | DONALD CRICHLOW |
| Drywall Nailing | 8/1/2023 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 8/1/2023 | Approved | CHARLES BOGHOSKHAN |
| Underground Mechanical | 8/16/2023 | Approved | MICHAEL LEWIS |
| Sewer | 8/22/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 8/22/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 9/18/2023 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Final | 10/18/2023 | Approved | MICHAEL LEWIS |
| Gas Test | 10/18/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 10/18/2023 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/18/2023 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 10/18/2023 | Approved | MICHAEL LEWIS |
| Final | 10/19/2023 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 10/19/2023 | Approved | MICHAEL LEWIS |
| HVAC-Final | 10/19/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 10/19/2023 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 10/19/2023 | Approved | MICHAEL LEWIS |