Permit Issued
Issued on 5/18/2023
Issuing Office
Current Status
CofO Issued on 5/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 SAM CHANG
Corrections Issued 10/7/2022 SAM CHANG
Quality Review Completed 10/12/2022 EUGENE BARBEAU
Applicant returned to address corrections 3/23/2023 SAM CHANG
Plan Check Approved 4/24/2023 SAM CHANG
Issued 5/18/2023 APPLICANT
CofO in Progress 5/2/2024 HAMIK HARTOUNIAN
Permit Finaled 5/6/2024 DEROLD HAUFF
CofO Issued 5/6/2024 DEROLD HAUFF
Permit Finaled 5/6/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/23/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 10/25/2022 JEANETTE VONG
Sewer availability Cleared 10/25/2022 JEANETTE VONG
Hydrant and Access approval Cleared 11/11/2022 JOHN CONNEALLY
CPC Cleared 1/13/2023 MICAELA TORRES-GIL
HPOZ Cleared 1/13/2023 MICAELA TORRES-GIL
Grading Pre-Inspection Cleared 3/23/2023 SAM CHANG
Low Impact Development Cleared 4/13/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 4/14/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/16/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/22/2023 Approved HAMIK HARTOUNIAN
Wood Frame 7/6/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 10/17/2023 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 10/17/2023 Approved ROY SPAULDING
HVAC-Rough 10/17/2023 Approved ROY SPAULDING
PLUMBING-Rough 10/17/2023 Not Ready for Inspection ROY SPAULDING
Verify Sprinkler Sign Off 10/17/2023 Approved ROY SPAULDING
Wood Frame 10/17/2023 Partial Approval ROY SPAULDING
PLUMBING-Rough 10/24/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/1/2023 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/6/2023 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/15/2023 Approved HAMIK HARTOUNIAN
Insulation 12/15/2023 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/19/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/10/2024 Partial Approval HAMIK HARTOUNIAN
Final 4/18/2024 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/18/2024 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 4/18/2024 Corrections Issued BRIAN SULLIVAN
Smoke Detectors 4/18/2024 Approved BRIAN SULLIVAN
Final 4/26/2024 OK to Issue CofO HAMIK HARTOUNIAN