602 W 80TH ST 1-2 90044

Certificate Information: 602 W 80TH ST 1-2 90044

Application / Permit
22010-10000-04406
Plan Check / Job No.
B22LA17593
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Eplan (N) 3-STORY DUPLEX (FRONT)
Permit Issued
Issued on 6/20/2023
Issuing Office
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 NGHI SU
Corrections Issued 9/29/2022 NGHI SU
Quality Review Completed 9/29/2022 GARO TELMI
Applicant returned to address corrections 5/19/2023 NGHI SU
Plan Check Approved 6/9/2023 NGHI SU
Issued 6/20/2023 APPLICANT
CofO in Progress 3/12/2025 JOHN QUINTANILLA
Permit Finaled 3/13/2025 DEROLD HAUFF
CofO Issued 3/13/2025 DEROLD HAUFF
Permit Finaled 3/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/5/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/6/2022 WALLIE JONG
"Q" conditions Cleared 10/12/2022 JAZMIN ROQUE
Hydrant and Access approval Cleared 11/10/2022 LAVEON RIDER
Sewer availability Cleared 1/27/2023 WALLIE JONG
SB8 RUD Cleared 4/3/2023 MARITESS GO
Frnt yard landscape/Water mgmt Cleared 4/7/2023 YINGSHI HUANG
Low Impact Development Cleared 5/9/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 5/10/2023 WALLIE JONG

Contact Information

Contractor G A Design Build; Lic. No.: 941130-B       ,
Engineer Alvarado,, Carlos Humberto; Lic. No.: C19857 745 N WALNUTHAVEN DR      WEST COVINA, CA 91790
Engineer Elia,, Victor Anthony; Lic. No.: C64803 40912 CARLENA LN      TEMECULA, CA 92591
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803
Landscape Architect Lee,, Cynthia; Lic. No.: LA2524 2029 VERDUGO BLVD STE 1020      MONTROSE, CA 91020

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/22/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 9/12/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 9/12/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Partial Approval MICHAEL LEWIS
Sewer 10/19/2023 Approved MICHAEL LEWIS
Underground Mechanical 10/19/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Partial Approval MICHAEL LEWIS
Underground Mechanical 11/1/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Corrections Issued MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Partial Approval MICHAEL LEWIS
HVAC-Rough 2/8/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 2/8/2024 Corrections Issued MICHAEL LEWIS
Deputy Wood Construction 3/11/2024 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/12/2024 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 3/12/2024 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 3/12/2024 Not Ready for Inspection JOSEPH MCGARRY
MERV13>=Rough 3/12/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 3/12/2024 Conditional Approval JOSEPH MCGARRY
Verify Sprinkler Sign Off 3/12/2024 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 4/2/2024 Corrections Issued MICHAEL LEWIS
HVAC-Rough 4/2/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 4/11/2024 No Access for Inspection MICHAEL LEWIS
Green Building Rough 4/11/2024 No Access for Inspection MICHAEL LEWIS
Verify Sprinkler Sign Off 4/11/2024 No Access for Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 4/16/2024 Approved MICHAEL LEWIS
Green Building Rough 4/16/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 4/16/2024 Approved MICHAEL LEWIS
Insulation 4/24/2024 Approved JOSH MEISTER
Drywall Nailing 5/14/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/29/2024 Approved CRAIG DAVIS
Gas Test 7/25/2024 Approved MICHAEL LEWIS
Final 2/14/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 2/14/2025 Not Ready for Inspection JOHN QUINTANILLA
MERV13>=Final 2/14/2025 Partial Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 2/14/2025 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 2/14/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 2/20/2025 Approved JOHN QUINTANILLA
Final 2/20/2025 Conditional Approval JOHN QUINTANILLA
Green Building Final 2/20/2025 Approved JOHN QUINTANILLA
HVAC-Final 2/20/2025 Approved JOHN QUINTANILLA
MERV13>=Final 2/20/2025 Approved JOHN QUINTANILLA
Service/Power Release 2/20/2025 Approved JOHN QUINTANILLA
Final 3/11/2025 OK to Issue CofO JOHN QUINTANILLA