1332 N SILVER LAKE BLVD 90026
Certificate Information: 1332 N SILVER LAKE BLVD 90026
- Application / Permit
- 22010-10000-04392
- Plan Check / Job No.
- B22LA17575
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 4/25/2023
- Issuing Office
- Current Status
- CofO Issued on 4/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2022 | SHANGQIN XIE |
| Corrections Issued | 9/9/2022 | SHANGQIN XIE |
| Applicant returned to address corrections | 11/4/2022 | SHANGQIN XIE |
| Applicant returned to address corrections | 3/28/2023 | SHANGQIN XIE |
| Applicant returned to address corrections | 4/17/2023 | SHANGQIN XIE |
| Plan Check Approved | 4/20/2023 | SHANGQIN XIE |
| Issued | 4/25/2023 | APPLICANT |
| CofO in Progress | 4/28/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 4/28/2025 | DEROLD HAUFF |
| CofO Issued | 4/28/2025 | DEROLD HAUFF |
| Permit Finaled | 4/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 9/22/2022 | PRISCILLA RUIZ |
| Grading Pre-Inspection | Cleared | 9/23/2022 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 9/28/2022 | STEVE MELGAR |
| Low Impact Development | Cleared | 3/13/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 3/16/2023 | STEVE MELGAR |
| Address approval | Cleared | 3/23/2023 | STEVE MELGAR |
| GPI Written Notices | Cleared | 3/24/2023 | JOHN FRANCIA |
| Construction near power lines | Cleared | 4/13/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/12/2024 | Corrections Issued | THOMAS LOGRASSO |
| Pre-Inspection | 3/12/2024 | Partial Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 3/19/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 4/3/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/29/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 4/29/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/1/2024 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 5/1/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 5/1/2024 | Corrections Issued | THOMAS LOGRASSO |
| Sewer | 5/1/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 5/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Sewer | 5/7/2024 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 5/7/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 5/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Sewer | 5/8/2024 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 5/9/2024 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 5/9/2024 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 5/10/2024 | Partial Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/10/2024 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 6/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/21/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/21/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/26/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 6/26/2024 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 6/26/2024 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 7/1/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/11/2024 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 7/11/2024 | Approved | ROY SPAULDING |
| Insulation | 7/11/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 7/29/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/29/2024 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/29/2024 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/31/2024 | Approved | ANTHONY RAMOS |
| Insulation | 8/1/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 8/6/2024 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 2/5/2025 | Corrections Issued | FREDDIE RIVERA |
| Service/Power Release | 2/5/2025 | Partial Inspection | FREDDIE RIVERA |
| Final | 2/13/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/13/2025 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 2/13/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 2/13/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/13/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 2/20/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 2/20/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 3/27/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 3/27/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 4/16/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 4/16/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 4/25/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 4/25/2025 | Not Required | HAMIK HARTOUNIAN |