564 N OCAMPO DR 90272
Certificate Information: 564 N OCAMPO DR 90272
- Application / Permit
- 22010-10000-04384
- Plan Check / Job No.
- B22LA17534
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- (N) 2-story w/ accessory living quarter and basement . 2 of 4
- Permit Issued
- Issued on 9/5/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 9/5/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | SAM CHANG |
| Corrections Issued | 10/4/2022 | SAM CHANG |
| Quality Review Completed | 10/4/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 11/4/2022 | APPLICANT |
| Applicant returned to address corrections | 12/5/2022 | SAM CHANG |
| Applicant returned to address corrections | 7/17/2023 | SAM CHANG |
| Applicant returned to address corrections | 7/31/2023 | SAM CHANG |
| Plan Check Approved | 8/18/2023 | SAM CHANG |
| Issued | 9/5/2023 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 11/16/2022 | DALIA MOKAYED |
| CPC | Cleared | 11/16/2022 | DALIA MOKAYED |
| CPC | Cleared | 11/16/2022 | DALIA MOKAYED |
| Miscellaneous | Cleared | 11/16/2022 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 12/2/2022 | GILBERT URREA |
| GPI Written Notices | Cleared | 12/5/2022 | SAM CHANG |
| Grading Pre-Inspection | Cleared | 12/5/2022 | SAM CHANG |
| Sewer availability | Cleared | 1/9/2023 | ANTHONY MAINEZ |
| Low Impact Development | Cleared | 7/11/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/24/2023 | AHMED AMARRAGY |
| Excavation more than 5-ft deep | Cleared | 7/31/2023 | CALOSHA APPROVED |
Contact Information
| Architect | Williger,, Paul Brant; Lic. No.: C24022 | 26176 FAIRSIDE ROAD MALIBU, CA 90265 |
| Contractor | E B R Construction Inc; Lic. No.: 941088-B | 5828 LOCKHURST DR WOODLAND HILLS, CA 91367 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/18/2023 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 10/25/2023 | Partial Approval | EVAN COOPER |
| Deputy Shotcrete | 11/20/2023 | Conditional Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 11/22/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Shotcrete | 11/28/2023 | Conditional Approval | EVAN COOPER |
| PLUMBING-Rough | 1/31/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 2/9/2024 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 2/29/2024 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 2/29/2024 | Approved | EVAN COOPER |
| Deputy Steel/Welding | 3/13/2024 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2024 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 4/26/2024 | Approved | EVAN COOPER |
| Deputy Steel/Welding | 5/3/2024 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 5/31/2024 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Corrections Issued | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 10/1/2024 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2024 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 11/13/2024 | Approved | EVAN COOPER |
| HVAC-Rough | 11/13/2024 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 11/13/2024 | Approved | EVAN COOPER |
| HVAC-Rough | 11/15/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/9/2024 | Corrections Issued | BOBBY KEY |
| Drywall Nailing | 12/9/2024 | Partial Approval | BOBBY KEY |
| Green Building Rough | 12/9/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/9/2024 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 12/9/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/18/2024 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 12/18/2024 | Partial Approval | ARAM AVEDISIAN |