10365 N COMMERCE AVE 91042
Certificate Information: 10365 N COMMERCE AVE 91042
- Application / Permit
- 22010-10000-04352
- Plan Check / Job No.
- B22LA17410
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING UNIT AT REAR OF LOT The building shall be equipped with an automatic residential fire sprinkler system in accordance with NFPA13D.
- Permit Issued
- Issued on 9/11/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | MONICA RAMIREZ |
| Corrections Issued | 9/22/2022 | MONICA RAMIREZ |
| Quality Review Completed | 9/22/2022 | RODOLFO ARIAS |
| Building Plans Picked Up | 9/26/2022 | APPLICANT |
| Applicant returned to address corrections | 1/25/2023 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/23/2023 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/21/2023 | MONICA RAMIREZ |
| Plan Check Approved | 6/6/2023 | MONICA RAMIREZ |
| Plan Check Approved | 9/8/2023 | MONICA RAMIREZ |
| Issued | 9/11/2023 | APPLICANT |
| CofO in Progress | 7/3/2025 | WILLIAM WREN |
| Permit Finaled | 8/4/2025 | RUBEN SALAS |
| CofO Issued | 8/4/2025 | RUBEN SALAS |
| Permit Finaled | 8/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/28/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 9/29/2022 | MEGAN GODINEZ |
| Miscellaneous | Cleared | 10/4/2022 | JAZMIN ROQUE |
| Highway dedication | Cleared | 11/14/2022 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 11/30/2022 | LAVEON RIDER |
| Grading Pre-Inspection | Cleared | 12/19/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 12/22/2022 | SARAH HOUNSELL |
| Low Impact Development | Cleared | 1/9/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 1/12/2023 | MEGAN GODINEZ |
| GPI Written Notices | Cleared | 1/25/2023 | ROBERT PINA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/14/2023 | Partial Inspection | WILLIAM WREN |
| Pre-Inspection | 9/18/2023 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 9/28/2023 | Partial Approval | WILLIAM WREN |
| Deputy Reinf. Concrete | 10/4/2023 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 10/4/2023 | Approved | WILLIAM WREN |
| Deputy Steel/Welding | 10/26/2023 | Conditional Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 10/30/2023 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 11/20/2023 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Partial Approval | WILLIAM WREN |
| Sewer | 11/20/2023 | Not Ready for Inspection | WILLIAM WREN |
| Structural Steel Frame | 11/20/2023 | Not Ready for Inspection | WILLIAM WREN |
| Underground Mechanical | 11/20/2023 | Partial Approval | WILLIAM WREN |
| Deputy Wood Construction | 12/13/2023 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 1/25/2024 | Partial Approval | MATTHEW NELSON |
| Sewer | 1/25/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Sewer | 1/31/2024 | Corrections Issued | CRAIG DAVIS |
| Underground Mechanical | 1/31/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 2/1/2024 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 2/14/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 2/21/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 2/21/2024 | Not Ready for Inspection | WILLIAM WREN |
| Sewer | 2/21/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 2/27/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/5/2024 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 3/5/2024 | Not Ready for Inspection | WILLIAM WREN |
| Verify Sprinkler Sign Off | 3/5/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 3/8/2024 | Approved | WILLIAM WREN |
| Insulation | 3/14/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/14/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Conditional Approval | WILLIAM WREN |
| Deputy Wood Construction | 3/19/2024 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 4/5/2024 | Approved | KIRK SANDERS |
| Shower Pan | 5/2/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 5/3/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 5/28/2024 | Approved | WILLIAM WREN |
| Shower Pan | 5/28/2024 | Approved | WILLIAM WREN |
| Underground Mechanical | 6/24/2024 | Partial Approval | WILLIAM WREN |
| Underground Mechanical | 9/10/2024 | Approved | WILLIAM WREN |
| Service/Power Release | 2/12/2025 | Approved | WILLIAM WREN |
| Final | 4/21/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 4/21/2025 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Required | WILLIAM WREN |
| Smoke Detectors | 4/21/2025 | Not Ready for Inspection | WILLIAM WREN |
| Final | 6/18/2025 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 6/18/2025 | Approved | WILLIAM WREN |
| Service/Power Release | 6/18/2025 | Approved | WILLIAM WREN |
| Smoke Detectors | 6/18/2025 | Approved | WILLIAM WREN |