3221 E LANFRANCO ST 90063
Certificate Information: 3221 E LANFRANCO ST 90063
- Application / Permit
- 22010-10000-04334
- Plan Check / Job No.
- B22LA15065
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN- NEW 2-STORY ADU WITH ATTACHED 2-CAR GARAGE PER LAMC 12.22 A.33 (c)-(d) CUGU- PUBLICLY HABITABLE SPACE
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- Current Status
- CofO Issued on 9/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/31/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/9/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 5/2/2023 | MAHNAZ NOURHASHEMI |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 9/9/2025 | FREDDIE RIVERA |
| No Progress | 9/13/2025 | DEROLD HAUFF |
| CofO in Progress | 9/13/2025 | DEROLD HAUFF |
| Permit Finaled | 9/18/2025 | DEROLD HAUFF |
| CofO Issued | 9/18/2025 | DEROLD HAUFF |
| Permit Finaled | 9/18/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 10/5/2022 | ADALBERTO VERA |
| Clean Up Green Up | Cleared | 10/13/2022 | RUBEN VASQUEZ |
| Address approval | Cleared | 10/14/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 10/21/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 11/18/2022 | KURT CORRAL |
| Permit | Cleared | 11/21/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 12/16/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 12/21/2022 | AMAAN MALIK |
| SB8 RUD | Cleared | 4/12/2023 | LOUIE MILLER |
| GPI Written Notices | Cleared | 4/28/2023 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 4/28/2023 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Lajoma Construction Inc; Lic. No.: 864461-B | 838 E 93RD ST LOS ANGELES, CA 90002 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/22/2023 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 6/22/2023 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 7/10/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2023 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2023 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Partial Approval | JUSTIN HAWLEY |
| Rough-Elec/Plmb/HVAC | 11/30/2023 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 12/13/2023 | Partial Approval | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 12/13/2023 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/21/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/21/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/21/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 12/21/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 12/28/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/19/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 2/8/2024 | Partial Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/8/2024 | Approved | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 12/18/2024 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Final | 4/15/2025 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 4/15/2025 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 5/7/2025 | Corrections Issued | FREDDIE RIVERA |
| Final | 5/7/2025 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/7/2025 | Approved | FREDDIE RIVERA |
| Green Building Final | 5/7/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 5/7/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 5/7/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/7/2025 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 5/7/2025 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 5/7/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 8/12/2025 | Approved | FREDDIE RIVERA |
| Final | 8/12/2025 | OK to Issue CofO | FREDDIE RIVERA |
| PLUMBING-Final | 8/12/2025 | Approved | FREDDIE RIVERA |
| Service/Power Release | 8/12/2025 | Approved | FREDDIE RIVERA |