3221 E LANFRANCO ST 90063

Certificate Information: 3221 E LANFRANCO ST 90063

Application / Permit
22010-10000-04334
Plan Check / Job No.
B22LA15065
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN- NEW 2-STORY ADU WITH ATTACHED 2-CAR GARAGE PER LAMC 12.22 A.33 (c)-(d) CUGU- PUBLICLY HABITABLE SPACE
Permit Issued
Issued on 5/25/2023
Issuing Office
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 MAHNAZ NOURHASHEMI
Corrections Issued 8/31/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 9/9/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 5/2/2023 MAHNAZ NOURHASHEMI
Issued 5/25/2023 APPLICANT
CofO in Progress 9/9/2025 FREDDIE RIVERA
No Progress 9/13/2025 DEROLD HAUFF
CofO in Progress 9/13/2025 DEROLD HAUFF
Permit Finaled 9/18/2025 DEROLD HAUFF
CofO Issued 9/18/2025 DEROLD HAUFF
Permit Finaled 9/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 10/5/2022 ADALBERTO VERA
Clean Up Green Up Cleared 10/13/2022 RUBEN VASQUEZ
Address approval Cleared 10/14/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 10/21/2022 AMAAN MALIK
Sewer availability Cleared 10/21/2022 AMAAN MALIK
Hydrant and Access approval Cleared 11/18/2022 KURT CORRAL
Permit Cleared 11/21/2022 AMAAN MALIK
Low Impact Development Cleared 12/16/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 12/21/2022 AMAAN MALIK
SB8 RUD Cleared 4/12/2023 LOUIE MILLER
GPI Written Notices Cleared 4/28/2023 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 4/28/2023 MAHNAZ NOURHASHEMI

Contact Information

Contractor Lajoma Construction Inc; Lic. No.: 864461-B 838 E 93RD ST      LOS ANGELES, CA 90002
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/22/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 6/22/2023 Partial Approval FREDDIE RIVERA
Underground Mechanical 6/22/2023 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 7/10/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 7/13/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Approval JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 11/30/2023 Corrections Issued FREDDIE RIVERA
HVAC-Rough 12/13/2023 Partial Approval FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 12/13/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 12/21/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/21/2023 Approved ENRIQUE MIRELES
Green Building Rough 12/21/2023 Approved ENRIQUE MIRELES
HVAC-Rough 12/21/2023 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 12/21/2023 Approved ENRIQUE MIRELES
Insulation 12/28/2023 Approved ENRIQUE MIRELES
Drywall Nailing 1/19/2024 Approved FREDDIE RIVERA
Drywall Nailing 2/8/2024 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 2/8/2024 Approved FREDDIE RIVERA
Deputy Reinf. Concrete 12/18/2024 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Final 4/15/2025 Corrections Issued FREDDIE RIVERA
HVAC-Final 4/15/2025 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 5/7/2025 Corrections Issued FREDDIE RIVERA
Final 5/7/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/7/2025 Approved FREDDIE RIVERA
Green Building Final 5/7/2025 Approved FREDDIE RIVERA
HVAC-Final 5/7/2025 Approved FREDDIE RIVERA
PLUMBING-Final 5/7/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/7/2025 SGSOV Approved FREDDIE RIVERA
Service/Power Release 5/7/2025 Partial Inspection FREDDIE RIVERA
Smoke Detectors 5/7/2025 Approved FREDDIE RIVERA
ELECTRICAL-Final 8/12/2025 Approved FREDDIE RIVERA
Final 8/12/2025 OK to Issue CofO FREDDIE RIVERA
PLUMBING-Final 8/12/2025 Approved FREDDIE RIVERA
Service/Power Release 8/12/2025 Approved FREDDIE RIVERA