6402 W COLGATE AVE 90048
Certificate Information: 6402 W COLGATE AVE 90048
- Application / Permit
- 22010-10000-04309
- Plan Check / Job No.
- B22LA17286
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/16/2023
- Issuing Office
- Current Status
- CofO Issued on 6/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | DANIEL YIP |
| Corrections Issued | 9/9/2022 | DANIEL YIP |
| Applicant returned to address corrections | 7/27/2023 | DANIEL YIP |
| Applicant returned to address corrections | 8/16/2023 | DANIEL YIP |
| Applicant returned to address corrections | 8/18/2023 | DANIEL YIP |
| Plan Check Approved | 11/16/2023 | DANIEL YIP |
| Issued | 11/16/2023 | APPLICANT |
| CofO in Progress | 6/25/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 6/26/2024 | DANIEL ORRANTE |
| CofO Issued | 6/26/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/26/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/8/2022 | TINA MIRANDA |
| Construction within easement | Cleared | 11/8/2022 | TINA MIRANDA |
| Address approval | Cleared | 11/9/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 11/14/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2023 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/12/2023 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/14/2023 | Partial Approval | MEL KHACHATOURIAN |
| Sewer | 1/4/2024 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 1/4/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/18/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Barrier | 1/24/2024 | Approved | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 1/30/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/7/2024 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 2/8/2024 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 2/8/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 2/8/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 2/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 3/29/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 3/29/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/29/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 4/4/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 4/8/2024 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/7/2024 | Approved | MEL KHACHATOURIAN |
| Final | 5/7/2024 | Corrections Issued | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2024 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 5/7/2024 | Approved | MEL KHACHATOURIAN |
| Final | 5/10/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Approved | MEL KHACHATOURIAN |