11850 W NORTH PARK AVE 90066
Certificate Information: 11850 W NORTH PARK AVE 90066
- Application / Permit
- 22010-10000-04292
- Plan Check / Job No.
- B22LA17260
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE [NFPA-13D FIRE SPRINKLERS THROUGHOUT]
- Permit Issued
- Issued on 11/8/2022
- Issuing Office
- Current Status
- CofO Issued on 10/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/6/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/13/2022 | STEVEN KIM |
| Applicant returned to address corrections | 11/1/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/7/2022 | NILOOFAR MEHRAIN |
| Issued | 11/8/2022 | APPLICANT |
| CofO in Progress | 9/28/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 10/4/2023 | DANIEL ORRANTE |
| CofO Issued | 10/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/12/2022 | VLADIMIR ARUTYUNYAN |
| Permit | Cleared | 9/12/2022 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2022 | VLADIMIR ARUTYUNYAN |
| ZA Case | Cleared | 9/15/2022 | DALIA MOKAYED |
| Sewer availability | Cleared | 9/16/2022 | VLADIMIR ARUTYUNYAN |
| Trees in Parkway | Cleared | 9/20/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/3/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/3/2022 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 10/7/2022 | JOHN CONNEALLY |
| Specific Plan | Cleared | 10/13/2022 | FREDDY GARCIA |
Contact Information
| Contractor | Mod Luxe Inc; Lic. No.: 1059519-B | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/7/2022 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 12/7/2022 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 12/7/2022 | Partial Inspection | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 12/30/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 12/30/2022 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 1/3/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/3/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 3/22/2023 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | Partial Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/26/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/26/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 4/26/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/26/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 5/4/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/4/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/8/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/8/2023 | Approved | JESUS RODRIGUEZ |
| Final | 5/8/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 5/8/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 5/15/2023 | Approved | HERBERT GIRON |
| Shower Pan | 5/15/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 5/22/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/22/2023 | Approved | JESUS RODRIGUEZ |
| Verify Rec and Parks Fee Memo | 5/22/2023 | Approved | JESUS RODRIGUEZ |
| Gas Test | 6/30/2023 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 6/30/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 7/3/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Final | 8/29/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/29/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/29/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 8/29/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/20/2023 | Corrections Issued | HERBERT GIRON |
| Final | 9/20/2023 | Corrections Issued | HERBERT GIRON |
| Service/Power Release | 9/20/2023 | Not Ready for Inspection | HERBERT GIRON |
| Smoke Detectors | 9/20/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 9/27/2023 | Approved | JESUS RODRIGUEZ |
| Final | 9/27/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Service/Power Release | 9/27/2023 | Approved | JESUS RODRIGUEZ |