5173 W 21ST ST 90016
Certificate Information: 5173 W 21ST ST 90016
- Application / Permit
- 22010-10000-04289
- Plan Check / Job No.
- B22LA17247
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU AT REAR OF THE LOT PER ENGINEER DESIGN per Ordinance LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 10/27/2023
- Issuing Office
- Metro
- Current Status
- Issued on 10/27/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | AUNG SOE |
| Corrections Issued | 9/7/2022 | AUNG SOE |
| Building Plans Picked Up | 9/9/2022 | APPLICANT |
| Plan Check Approved | 12/8/2022 | RICARDO RAMIREZ |
| Issued | 10/27/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 9/15/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 10/24/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/1/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 11/7/2022 | STEVE MELGAR |
Contact Information
| Architect | Karen, Varhlick; Lic. No.: C38744 | , |
| Contractor | Owner-Builder | , |
| Engineer | Deihimi,, Amir Hossein; Lic. No.: C78194 | 23172 PLAZA POINTE DR STE 145 LAGUNA HILLS, CA 92653 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Sewer | 6/9/2026 |
| HVAC-Final | 6/9/2026 |
| ELECTRICAL-Final | 6/9/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/1/2024 | Partial Approval | ARTHUR NEGRETE |
| Underground Mechanical | 7/1/2024 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 7/11/2024 | Approved | ARTHUR NEGRETE |
| Deputy Reinf. Concrete | 7/15/2024 | Conditional Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 10/31/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 10/31/2024 | Partial Approval | ARTHUR NEGRETE |
| HVAC-Rough | 12/13/2024 | Corrections Issued | ARTHUR NEGRETE |
| PLUMBING-Rough | 12/13/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 12/20/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 1/3/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 1/3/2025 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 1/3/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 3/18/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 3/18/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 4/23/2026 | Approved | OSVALDO PARAMO |
| Shower Pan | 4/24/2026 | Corrections Issued | OSVALDO PARAMO |
| Drywall Nailing | 5/1/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 5/1/2026 | Corrections Issued | GEM DE OCAMPO |
| Shower Pan | 5/1/2026 | Approved | GEM DE OCAMPO |
| Interior/Exterior Lathing | 5/11/2026 | Approved | JUSTIN HAWLEY |