4121 1/2 W 62ND ST 90043

Certificate Information: 4121 1/2 W 62ND ST 90043

Application / Permit
22010-10000-04286
Plan Check / Job No.
B22LA17236
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan Converting Existing Garage into an ADU ADU CHECKED PER GCS 65852.2(E)(1)(A)
Permit Issued
Issued on 12/22/2022
Issuing Office
Current Status
CofO Issued on 6/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 SUNMIN LEE
Corrections Issued 10/7/2022 SUNMIN LEE
Applicant returned to address corrections 11/15/2022 SUNMIN LEE
Applicant returned to address corrections 11/21/2022 SUNMIN LEE
Applicant returned to address corrections 11/30/2022 SUNMIN LEE
Applicant returned to address corrections 12/17/2022 SUNMIN LEE
Plan Check Approved 12/21/2022 SUNMIN LEE
Issued 12/22/2022 APPLICANT
CofO in Progress 6/13/2023 ENRIQUE MIRELES
Permit Finaled 6/18/2023 DEROLD HAUFF
CofO Issued 6/18/2023 DEROLD HAUFF
Permit Finaled 6/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/3/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/3/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 11/3/2022 JEANIE LAM
Sewer availability Cleared 11/3/2022 JEANIE LAM
Grading Pre-Inspection Cleared 11/14/2022 KIRK LINKLATER

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/25/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/14/2023 Approved ENRIQUE MIRELES
HVAC-Rough 2/24/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/1/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/1/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/7/2023 Approved ENRIQUE MIRELES
Insulation 3/7/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/7/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Approved ENRIQUE MIRELES
Wood Frame 3/9/2023 Approved ENRIQUE MIRELES
Drywall Nailing 3/15/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/22/2023 Approved ENRIQUE MIRELES
Shower Pan 4/4/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/11/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/13/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/18/2023 Approved ENRIQUE MIRELES
Final 5/18/2023 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 5/18/2023 Approved ENRIQUE MIRELES
Pre-Inspection 5/23/2023 Corrections Issued ENRIQUE MIRELES
Final 6/7/2023 OK to Issue CofO ENRIQUE MIRELES