1357 W 23RD ST 1-4 90007
Certificate Information: 1357 W 23RD ST 1-4 90007
- Application / Permit
- 22010-10000-04279
- Plan Check / Job No.
- B22LA17210
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) STORAGE ROOM AND GARAGE OF (E) APARTMENT BUILDING TO ACCESSORY DWELLING UNIT (550 SQ FT) PER GCS 65852.2(e)(1)(C)
- Permit Issued
- Issued on 8/15/2023
- Issuing Office
- Current Status
- CofO Issued on 10/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 9/3/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 10/18/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 10/18/2022 | PINANK PATEL |
| Plan Check Approved | 10/22/2022 | JEROME MAGAT PALMA |
| Issued | 8/15/2023 | APPLICANT |
| CofO in Progress | 10/2/2024 | MARTIN TAVITIAN |
| CofO Issued | 10/2/2024 | ERNESTO CORRAL |
| Permit Finaled | 10/2/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/20/2022 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/20/2022 | DANIEL CORONADO |
| Address approval | Cleared | 9/21/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 9/21/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2022 | AMAAN MALIK |
| HPOZ | Cleared | 10/3/2022 | DEEPEAKA DHALIWAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Ting-Wei; Lic. No.: C91854 | 4541 MYRA AVE CYPRESS, CA 90630 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/19/2023 | Corrections Issued | ALAN MORELOS |
| Pre-Inspection | 10/24/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Deputy Drilled-In Anchors | 11/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 11/13/2023 | Partial Approval | LUIS CCAMACHO |
| Deputy Reinf. Concrete | 11/28/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 2/28/2024 | Partial Approval | ALFREDO LOPEZ |
| Green Building Rough | 2/28/2024 | Approved | ALFREDO LOPEZ |
| Wood Frame | 2/28/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 5/10/2024 | Approved | ALFREDO LOPEZ |
| Insulation | 5/16/2024 | Approved | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 5/16/2024 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 5/24/2024 | Approved | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 5/24/2024 | Approved | ALFREDO LOPEZ |
| Final | 8/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 8/30/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 8/30/2024 | Partial Inspection | ALFREDO LOPEZ |
| Final | 9/30/2024 | OK to Issue CofO | MARTIN TAVITIAN |
| Smoke Detectors | 9/30/2024 | Approved | MARTIN TAVITIAN |