1129 E PALMS BLVD 90291
Certificate Information: 1129 E PALMS BLVD 90291
- Application / Permit
- 22010-10000-04227
- Plan Check / Job No.
- B22LA16920
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 1/3/2024
- Issuing Office
- Metro
- Current Status
- Issued on 1/3/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | JAD BASMA |
| Corrections Issued | 9/5/2022 | JAD BASMA |
| Quality Review Completed | 9/13/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 10/4/2022 | JAD BASMA |
| Applicant returned to address corrections | 7/3/2023 | JAD BASMA |
| Plan Check Approved | 7/17/2023 | JAD BASMA |
| Issued | 1/3/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/5/2023 | JEREMY CHOK |
| Hydrant and Access approval | Cleared | 5/1/2023 | KURT CORRAL |
| Specific Plan | Cleared | 5/22/2023 | JIMMY VIVAR |
| Sewer availability | Cleared | 5/23/2023 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 6/5/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 6/20/2023 | TOMMY YIN |
| Permit | Cleared | 6/27/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 6/27/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Technick Construction; Lic. No.: 915758-B | 3198 E LA PALMA AVE ANAHEIM, CA 92806 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/4/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 6/4/2024 | Corrections Issued | HERBERT GIRON |
| Grading Pre-Inspection | 6/6/2024 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 2/24/2025 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 3/4/2025 | Corrections Issued | HERBERT GIRON |
| Pre-Inspection | 3/6/2025 | No Access for Inspection | HERBERT GIRON |
| Pre-Inspection | 3/11/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/20/2025 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/20/2025 | Approved | JESUS RODRIGUEZ |
| Pre-Inspection | 3/20/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 5/6/2025 | Not Ready for Inspection | BOBBY KEY |
| Sewer | 5/6/2025 | Partial Approval | BOBBY KEY |
| Structural Steel Frame | 5/6/2025 | Conditional Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 5/6/2025 | Not Ready for Inspection | BOBBY KEY |
| Deputy Drilled-In Anchors | 5/16/2025 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/20/2025 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/25/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 9/25/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/25/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 11/6/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/6/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/6/2025 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 11/6/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 1/21/2026 | Corrections Issued | RUBEN RIVAS |
| Insulation | 1/30/2026 | Approved | ANTHONY EGSON |
| Drywall Nailing | 2/18/2026 | Partial Approval | RUBEN RIVAS |
| Interior/Exterior Lathing | 2/18/2026 | Partial Approval | RUBEN RIVAS |