1129 E PALMS BLVD 90291

Certificate Information: 1129 E PALMS BLVD 90291

Application / Permit
22010-10000-04227
Plan Check / Job No.
B22LA16920
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 1/3/2024
Issuing Office
Metro
Current Status
Issued on 1/3/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/23/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 JAD BASMA
Corrections Issued 9/5/2022 JAD BASMA
Quality Review Completed 9/13/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 10/4/2022 JAD BASMA
Applicant returned to address corrections 7/3/2023 JAD BASMA
Plan Check Approved 7/17/2023 JAD BASMA
Issued 1/3/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/5/2023 JEREMY CHOK
Hydrant and Access approval Cleared 5/1/2023 KURT CORRAL
Specific Plan Cleared 5/22/2023 JIMMY VIVAR
Sewer availability Cleared 5/23/2023 HISASHI KOBAYAKAWA
Trees in Parkway Cleared 6/5/2023 ADALBERTO VERA
Low Impact Development Cleared 6/20/2023 TOMMY YIN
Permit Cleared 6/27/2023 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 6/27/2023 ANTHONY MAINEZ

Contact Information

Contractor Technick Construction; Lic. No.: 915758-B 3198 E LA PALMA AVE      ANAHEIM, CA 92806

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/4/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 6/4/2024 Corrections Issued HERBERT GIRON
Grading Pre-Inspection 6/6/2024 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 2/24/2025 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 3/4/2025 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 3/4/2025 Corrections Issued HERBERT GIRON
Pre-Inspection 3/6/2025 No Access for Inspection HERBERT GIRON
Pre-Inspection 3/11/2025 Corrections Issued JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/20/2025 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 3/20/2025 Approved JESUS RODRIGUEZ
Pre-Inspection 3/20/2025 Approved JESUS RODRIGUEZ
Green Building Rough 5/6/2025 Not Ready for Inspection BOBBY KEY
Sewer 5/6/2025 Partial Approval BOBBY KEY
Structural Steel Frame 5/6/2025 Conditional Approval BOBBY KEY
Verify Sprinkler Sign Off 5/6/2025 Not Ready for Inspection BOBBY KEY
Deputy Drilled-In Anchors 5/16/2025 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 5/20/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Partial Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 9/25/2025 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/25/2025 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 9/25/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 9/25/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 11/6/2025 Approved JESUS RODRIGUEZ
Green Building Rough 11/6/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/6/2025 Approved JESUS RODRIGUEZ
Shower Pan 11/6/2025 Approved JESUS RODRIGUEZ
Insulation 1/21/2026 Corrections Issued RUBEN RIVAS
Insulation 1/30/2026 Approved ANTHONY EGSON
Drywall Nailing 2/18/2026 Partial Approval RUBEN RIVAS
Interior/Exterior Lathing 2/18/2026 Partial Approval RUBEN RIVAS