428-428 1/2 N FULLER AVE 90036

Certificate Information: 428-428 1/2 N FULLER AVE 90036

Application / Permit
22010-10000-04213
Plan Check / Job No.
B22LA16865
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: New 2-story single family dwelling with an attached 1-story ADU. See Cooment.
Permit Issued
Issued on 8/11/2024
Issuing Office
Current Status
CofO Issued on 3/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 TSE MING HUANG
Corrections Issued 10/19/2022 TSE MING HUANG
Quality Review Completed 10/20/2022 EUGENE BARBEAU
Plan Check Approved 6/6/2023 TSE MING HUANG
Plan Check Approved 1/4/2024 TSE MING HUANG
Plan Check Approved 1/11/2024 JOHN FRANCIA
Plan Check Approved 1/12/2024 JOHN FRANCIA
Issued 8/11/2024 APPLICANT
CofO in Progress 3/27/2026 JOSH MEISTER
Permit Finaled 3/30/2026 DEROLD HAUFF
CofO Issued 3/30/2026 DEROLD HAUFF
Permit Finaled 3/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/1/2022 STEVE MELGAR
Hydrant and Access approval Cleared 11/18/2022 MATTHEW CRAIG
Low Impact Development Cleared 12/15/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/27/2022 AMAAN MALIK
Sewer availability Cleared 1/17/2023 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/24/2023 AMAAN MALIK
SB8 RUD Cleared 3/21/2023 NICHOLAS KAWAZOE
Miscellaneous Cleared 4/24/2023 RYAN LY

Contact Information

Architect Woodcraft,, Lawrence Albert; Lic. No.: C23651 20812 VENTURA BLVD, STE 205      WOODLAND HILLS, CA 91364
Contractor Rebah Maintenance Services Inc; Lic. No.: 1069019-B       ,
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/1/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 11/6/2024 Partial Inspection JOSE MACIAS
METHANE-Barrier 11/6/2024 Not Ready for Inspection JOSE MACIAS
METHANE-Subgrade 11/6/2024 Not Ready for Inspection JOSE MACIAS
Excavation/Setback/Form/Re-Bar 11/21/2024 Approved JOSE MACIAS
METHANE-Subgrade 11/21/2024 Approved JOSE MACIAS
Deputy Reinf. Concrete 11/22/2024 Conditional Approval JOSE MACIAS
Deputy Methane Barrier 12/2/2024 Conditional Approval JOSE MACIAS
Footing/Foundation/Slab 12/4/2024 Approved JOSE MACIAS
METHANE-Barrier 12/4/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Conditional Approval JOSE MACIAS
PLUMBING-Rough 3/26/2025 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Approved ENRIQUE MIRELES
HVAC-Rough 5/12/2025 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/19/2025 Approved JOSE MACIAS
ELECTRICAL-Rough 5/22/2025 Approved JOSE MACIAS
Pre-Inspection 5/22/2025 Partial Inspection RAUL BARAJAS
Green Building Rough 6/11/2025 No Access for Inspection JOSE MACIAS
METHANE-Rough 6/11/2025 No Access for Inspection JOSE MACIAS
Verify Sprinkler Sign Off 6/11/2025 No Access for Inspection JOSE MACIAS
BUILDING-Rough-Frame 6/13/2025 Corrections Issued JOSE MACIAS
Green Building Rough 6/13/2025 Approved JOSE MACIAS
Insulation 6/13/2025 Corrections Issued JOSE MACIAS
METHANE-Rough 6/13/2025 Approved JOSE MACIAS
Verify Sprinkler Sign Off 6/13/2025 Approved JOSE MACIAS
Insulation 6/18/2025 Approved JOSE MACIAS
Drywall Nailing 6/30/2025 Corrections Issued JOSE MACIAS
Drywall Nailing 7/3/2025 Approved JOSE MACIAS
Shower Pan 8/5/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 8/11/2025 Approved JOSH MEISTER
BUILDING-Rough-Frame 12/12/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/12/2025 Approved ENRIQUE MIRELES
Final 12/12/2025 Corrections Issued ENRIQUE MIRELES
Green Building Final 12/12/2025 Approved ENRIQUE MIRELES
HVAC-Final 12/12/2025 Approved ENRIQUE MIRELES
PLUMBING-Final 12/12/2025 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 12/12/2025 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 12/12/2025 Approved ENRIQUE MIRELES
Final 12/17/2025 Corrections Issued JOSH MEISTER
Service/Power Release 12/17/2025 Not Ready for Inspection JOSH MEISTER
Special/Order Compliance 12/17/2025 Partial Inspection JOSH MEISTER
Special/Order Compliance 1/26/2026 Corrections Issued JOSH MEISTER
Gas Test 2/13/2026 Approved JOSH MEISTER
Final 3/17/2026 Corrections Issued JOSH MEISTER
Service/Power Release 3/17/2026 Not Ready for Inspection JOSH MEISTER
Final 3/18/2026 Not Ready for Inspection JOSH MEISTER
Final 3/24/2026 OK to Issue CofO JOSH MEISTER
Service/Power Release 3/24/2026 Approved JOSH MEISTER