3548 1/2 N COPELAND PL 90032
Certificate Information: 3548 1/2 N COPELAND PL 90032
- Application / Permit
- 22010-10000-04151
- Plan Check / Job No.
- B22LA16611
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY ADU 1,200 SF (33 X 40) 2 of 2
- Permit Issued
- Issued on 3/7/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 9/14/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 9/21/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 2/27/2023 | MARCELA FRANQUEZ |
| Issued | 3/7/2023 | APPLICANT |
| CofO in Progress | 3/29/2024 | LILIANA PORTILLO |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
| CofO Issued | 4/16/2024 | DEROLD HAUFF |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/1/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2022 | JEANIE LAM |
| Sewer availability | Cleared | 11/2/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 1/11/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/13/2023 | WALLIE JONG |
| GPI Written Notices | Cleared | 2/27/2023 | MARCELA FRANQUEZ |
| Grading Pre-Inspection | Cleared | 2/27/2023 | MANUEL TEJADA |
Contact Information
| Contractor | Safe Quake Construction; Lic. No.: 571102-B | 2088 S ATLANTIC BL #291 MONTEREY PARK, CA 91754 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/19/2023 | Not Ready for Inspection | AMY COLIN |
| PLUMBING-Rough | 4/20/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 4/25/2023 | Corrections Issued | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Partial Approval | AMY COLIN |
| Sewer | 7/17/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 7/18/2023 | Partial Approval | AMY COLIN |
| ELECTRICAL-Rough | 7/18/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 7/18/2023 | Approved | AMY COLIN |
| Sewer | 7/18/2023 | Approved | AMY COLIN |
| Underground Mechanical | 7/18/2023 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 8/9/2023 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 8/9/2023 | Approved | AMY COLIN |
| Green Building Rough | 8/9/2023 | Approved | AMY COLIN |
| HVAC-Rough | 8/9/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 8/9/2023 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 8/9/2023 | Corrections Issued | AMY COLIN |
| Insulation | 8/22/2023 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 8/22/2023 | Approved | AMY COLIN |
| Drywall Nailing | 9/6/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 9/28/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 1/31/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 1/31/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 1/31/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 2/8/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/8/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/8/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/19/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/21/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 3/21/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 3/21/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 3/21/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Service/Power Release | 3/21/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/28/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/28/2024 | Approved | LILIANA PORTILLO |
| Final | 3/28/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/28/2024 | Approved | LILIANA PORTILLO |
| Green Building Final | 3/28/2024 | Approved | LILIANA PORTILLO |
| HVAC-Final | 3/28/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 3/28/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 3/28/2024 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 3/28/2024 | Approved | LILIANA PORTILLO |