1305 W 35TH PL 90007
Certificate Information: 1305 W 35TH PL 90007
- Application / Permit
- 22010-10000-04135
- Plan Check / Job No.
- B22LA16527
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2 of 2 (1) NEW 2 STORY ADU/GARAGE @ REAR OF LOT R3 OCCUPANCY 694 SQ FT U OCCUPANCY 156 SQ FT per 12.22A33 (c) and (d)
- Permit Issued
- Issued on 12/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 8/27/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 9/7/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 9/20/2022 | APPLICANT |
| Applicant returned to address corrections | 11/15/2022 | MARCELA FRANQUEZ |
| Plan Check Approved | 12/1/2022 | MARCELA FRANQUEZ |
| Issued | 12/9/2022 | APPLICANT |
| CofO in Progress | 1/29/2024 | SABAS ALONSO |
| CofO Issued | 2/14/2024 | DEROLD HAUFF |
| Permit Finaled | 2/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/10/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2022 | CELINA MORENO |
| Permit | Cleared | 11/17/2022 | CELINA MORENO |
| Sewer availability | Cleared | 11/17/2022 | CELINA MORENO |
| Low Impact Development | Cleared | 11/21/2022 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 11/29/2022 | TREVOR QUAN |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/14/2023 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/14/2023 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Barrier | 2/14/2023 | Approved | ALEJANDRO DE ARTOLA |
| METHANE-Subgrade | 2/14/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 3/1/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2023 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 5/31/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/31/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 6/7/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/7/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/8/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 6/8/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/8/2023 | Partial Approval | SABAS ALONSO |
| METHANE-Rough | 6/8/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 6/8/2023 | Approved | SABAS ALONSO |
| Insulation | 6/12/2023 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 6/22/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/18/2023 | Approved | BRENDAN MORELLI |
| Sewer | 8/23/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/23/2023 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/1/2023 | Approved | SABAS ALONSO |
| Smoke Detectors | 9/1/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 9/14/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/14/2023 | Approved | SABAS ALONSO |
| Final | 10/6/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 10/6/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 10/6/2023 | Approved | SABAS ALONSO |
| Final | 10/25/2023 | Corrections Issued | SABAS ALONSO |
| Insulation | 12/1/2023 | Corrections Issued | SABAS ALONSO |
| Final | 1/23/2024 | OK to Issue CofO | SABAS ALONSO |