312 E GAGE AVE 90003
Certificate Information: 312 E GAGE AVE 90003
- Application / Permit
- 22010-10000-04123
- Plan Check / Job No.
- B22LA16475
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU 1,200 SQFT 1 -STORY PER ORDINANCE AND LAMC 12.22 A33(c)&(d). **Demo of Carport under permit #22019-10000-03885 NOT APPROVED UNDER THIS PERMIT
- Permit Issued
- Issued on 12/22/2023
- Issuing Office
- Metro
- Current Status
- Issued on 12/22/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | ZAW HAN |
| Corrections Issued | 8/23/2022 | ZAW HAN |
| Building Plans Picked Up | 10/25/2022 | APPLICANT |
| Applicant returned to address corrections | 6/16/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 12/12/2023 | NEHEMIAS RAMOS |
| Issued | 12/22/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2023 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2023 | ABEL CASILLAS |
| Sewer availability | Cleared | 6/28/2023 | ABEL CASILLAS |
| Low Impact Development | Cleared | 10/24/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 12/4/2023 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gutierrez, Martinez, Carlos; Lic. No.: C92266 | 4619 BOGART AVE BALDWIN PARK, CA 91706 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/27/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/27/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 12/27/2023 | Partial Approval | MICHAEL LEWIS |
| Sewer | 12/27/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 12/27/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 2/23/2024 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 2/23/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 2/23/2024 | Approved | MICHAEL LEWIS |
| Shower Pan | 2/23/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 3/6/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 3/6/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 3/6/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 3/8/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 3/8/2024 | Approved | MICHAEL LEWIS |
| Insulation | 3/15/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 3/22/2024 | Approved | STUART CHAPMAN |
| Underground Mechanical | 5/10/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/11/2024 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 8/19/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 8/19/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 8/19/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Service/Power Release | 8/19/2024 | Corrections Issued | MICHAEL LEWIS |
| Smoke Detectors | 8/19/2024 | Approved | MICHAEL LEWIS |
| Final | 9/12/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Service/Power Release | 9/12/2024 | Partial Approval | MICHAEL LEWIS |
| Final | 8/11/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Service/Power Release | 8/11/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 8/28/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Service/Power Release | 8/28/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 12/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| Gas Test | 12/10/2025 | Approved | JOHN QUINTANILLA |
| Final | 6/2/2026 | Conditional Approval | JOHN QUINTANILLA |
| Service/Power Release | 6/2/2026 | Approved | JOHN QUINTANILLA |