3637-3637 1/2 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3637-3637 1/2 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 22010-10000-04115
- Plan Check / Job No.
- B22LA16454
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW, 2 STORY 4876 SF TWO STORY SINGLE FAMILY RESIDENCE WITH ATTACHED 2 CAR GARAGE AND ATTACHED ADU PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 5/24/2023
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | NGHI SU |
| Corrections Issued | 8/29/2022 | NGHI SU |
| Quality Review Completed | 9/2/2022 | FARUK SEZER |
| Building Plans Picked Up | 9/7/2022 | APPLICANT |
| Applicant returned to address corrections | 11/1/2022 | NGHI SU |
| Plan Check Approved | 5/18/2023 | NGHI SU |
| Issued | 5/24/2023 | APPLICANT |
| CofO in Progress | 5/11/2026 | MICHAEL LEWIS |
| No Progress | 5/16/2026 | DAVID FEILER |
| CofO in Progress | 5/16/2026 | DAVID FEILER |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2022 | DINAH GARIN |
| Permit | Cleared | 9/16/2022 | DINAH GARIN |
| Specific Plan | Cleared | 9/27/2022 | EDUARDO HERMOSO |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2022 | DINAH GARIN |
| Sewer availability | Cleared | 9/28/2022 | DINAH GARIN |
| Frnt yard landscape/Water mgmt | Cleared | 9/30/2022 | SPENCER WEJROWSKI |
| Hydrant and Access approval | Cleared | 10/7/2022 | JOHN CONNEALLY |
| SB8 RUD | Cleared | 12/22/2022 | DORIS KWOK |
| Low Impact Development | Cleared | 4/19/2023 | ROGELIO CORTES |
| GPI Written Notices | Cleared | 5/10/2023 | NGHI SU |
| Grading Pre-Inspection | Cleared | 5/10/2023 | NGHI SU |
| Roof/Waste drainage to street | Cleared | 5/10/2023 | JASON NG |
Contact Information
| Architect | , ; Lic. No.: C35558 | 504 FLORAL PARK TERRACE SOUTH PASADENA, CA 91030 |
| Contractor | Time To Build Inc A; Lic. No.: 838931-B | 23037 BIRCH GLEN CIRCLE VALENCIA, CA 91354 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Rybak,, Richard; Lic. No.: GE2131 | 20312 TAU PLACE CHATSWORTH, CA 91311 |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
| Landscape Architect | Zock,, Diana; Lic. No.: LA5880 | 735 SUPERBA AVENUE VENICE, CA 90291 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/6/2023 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 7/28/2023 | Corrections Issued | JESUS PINEDA |
| Underground Mechanical | 9/27/2023 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 10/20/2023 | Partial Approval | EVAN COOPER |
| Underground Mechanical | 10/20/2023 | Partial Approval | EVAN COOPER |
| Deputy Other (see comments) | 11/3/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/6/2023 | Partial Approval | JESUS PINEDA |
| Deputy Shotcrete | 11/8/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Other (see comments) | 12/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 12/14/2023 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 12/15/2023 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 1/29/2024 | Partial Approval | KENNETH NAGLE |
| Deputy Reinf. Concrete | 1/30/2024 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 2/15/2024 | Partial Approval | JESUS PINEDA |
| Deputy Reinf. Concrete | 2/26/2024 | Conditional Approval | JESUS PINEDA |
| Underground Mechanical | 3/12/2024 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 3/22/2024 | Partial Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 3/26/2024 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 4/3/2024 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 4/9/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 5/15/2024 | Conditional Approval | JESUS PINEDA |
| Deputy Steel/Welding | 5/17/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Corrections Issued | HERBERT GIRON |
| Deputy Steel/Welding | 5/31/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 6/3/2024 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Partial Approval | JESUS RODRIGUEZ |
| Deputy Steel/Welding | 6/24/2024 | No Access for Inspection | KENNETH NAGLE |
| Deputy Steel/Welding | 7/2/2024 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Corrections Issued | JESUS PINEDA |
| Deputy Wood Construction | 7/12/2024 | Conditional Approval | JESUS PINEDA |
| Deputy Steel/Welding | 7/15/2024 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Partial Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Partial Approval | JESUS PINEDA |
| Deputy Steel/Welding | 11/19/2024 | Conditional Approval | DANIEL VERA |
| Deputy Steel/Welding | 12/17/2024 | Conditional Approval | DANIEL VERA |
| ELECTRICAL-Rough | 4/1/2025 | Partial Approval | WILBER ROSALES |
| HVAC-Rough | 4/1/2025 | Partial Approval | WILBER ROSALES |
| PLUMBING-Rough | 4/1/2025 | Partial Approval | WILBER ROSALES |
| Pre-Inspection | 4/25/2025 | Partial Inspection | WILBER ROSALES |
| ELECTRICAL-Rough | 7/2/2025 | Approved | WILBER ROSALES |
| Footing/Foundation/Slab | 7/17/2025 | Corrections Issued | WILBER ROSALES |
| Masonry Wall/Backfill | 7/17/2025 | Corrections Issued | WILBER ROSALES |
| Footing/Foundation/Slab | 7/23/2025 | Corrections Issued | KIRK SANDERS |
| Masonry Wall/Backfill | 7/23/2025 | Not Ready for Inspection | KIRK SANDERS |
| Pre-Inspection | 8/6/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Pre-Inspection | 8/13/2025 | Approved | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 8/21/2025 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 9/10/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 9/10/2025 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 9/10/2025 | Approved | BOBBY KEY |
| Green Building Rough | 9/10/2025 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 9/10/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 9/15/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 9/15/2025 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 10/2/2025 | Approved | JAYLIN GRAVITTE |
| Shower Pan | 10/6/2025 | Approved | JAYLIN GRAVITTE |
| Pre-Inspection | 2/2/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Pre-Inspection | 2/3/2026 | Partial Inspection | ARAM AVEDISIAN |
| Gas Test | 3/4/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/4/2026 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/4/2026 | SGSOV Approved | EVAN COOPER |
| ELECTRICAL-Final | 3/6/2026 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/13/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Service/Power Release | 3/13/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Final | 3/17/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 3/17/2026 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/18/2026 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 3/18/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 3/19/2026 | Corrections Issued | ARAM AVEDISIAN |
| Service/Power Release | 3/31/2026 | Approved | ANDREW NAVE |
| HVAC-Final | 4/16/2026 | Corrections Issued | HERBERT GIRON |
| Final | 4/20/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/20/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 4/23/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/23/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 4/23/2026 | Partial Approval | EUGENE CASSIDY |
| HVAC-Final | 5/7/2026 | Approved | EUGENE CASSIDY |
| Final | 5/8/2026 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 5/8/2026 | Approved | MICHAEL LEWIS |
| Special/Order Compliance | 5/18/2026 | Corrections Issued | MICHAEL LEWIS |