5151 S ARLINGTON AVE 90043
Certificate Information: 5151 S ARLINGTON AVE 90043
- Application / Permit
- 22010-10000-04113
- Plan Check / Job No.
- B22LA16447
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW DETTACHED 1003sf ADU ADU CHECKED PER LAMC 12.22 A.33(C) AND (D)
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- Current Status
- CofO Issued on 7/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | SUNMIN LEE |
| Corrections Issued | 9/6/2022 | SUNMIN LEE |
| Quality Review Completed | 9/9/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 12/23/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 2/14/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 2/24/2023 | SUNMIN LEE |
| Plan Check Approved | 2/27/2023 | SUNMIN LEE |
| Issued | 3/9/2023 | APPLICANT |
| CofO in Progress | 7/28/2025 | LUIS CASTRO |
| Permit Finaled | 7/28/2025 | DEROLD HAUFF |
| CofO Issued | 7/28/2025 | DEROLD HAUFF |
| Permit Finaled | 7/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/1/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 10/7/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 12/5/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 1/3/2023 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/1/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/1/2024 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/9/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/22/2024 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 5/22/2024 | Corrections Issued | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 5/22/2024 | Approved | ANTHONY EGSON |
| Insulation | 5/28/2024 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/30/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Partial Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/26/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/26/2024 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 9/3/2024 | Conditional Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/4/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 9/4/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Shower Pan | 9/4/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 10/1/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/9/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 10/9/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/11/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 10/11/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/16/2024 | Approved | ANTHONY EGSON |
| Insulation | 11/8/2024 | Not Ready for Inspection | JOSH MEISTER |
| Insulation | 11/14/2024 | Approved | BARRY HACHE |
| Drywall Nailing | 11/19/2024 | Approved | ANTHONY RAMOS |
| Underground Mechanical | 2/28/2025 | Approved | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 3/28/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 3/28/2025 | Not Ready for Inspection | LUIS CASTRO |
| Underground Mechanical | 4/4/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 5/1/2025 | Approved | LUIS CASTRO |
| Final | 5/1/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 5/1/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 5/1/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 5/1/2025 | SGSOV Approved | LUIS CASTRO |
| Service/Power Release | 5/1/2025 | Approved | LUIS CASTRO |
| Smoke Detectors | 5/1/2025 | Approved | LUIS CASTRO |
| Final | 6/26/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 7/23/2025 | Not Ready for Inspection | LUIS CASTRO |
| Final | 7/25/2025 | OK to Issue CofO | LUIS CASTRO |