2809-2811 W 46TH ST 90043

Certificate Information: 2809-2811 W 46TH ST 90043

Application / Permit
22010-10000-04091
Plan Check / Job No.
B22LA16316
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Construction of 2 new ADUs at the rear yard of the existing duplex. ADUs pe rGCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d) and (g)
Permit Issued
Issued on 9/5/2023
Issuing Office
Current Status
CofO Issued on 12/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 MARCELA FRANQUEZ
Corrections Issued 9/2/2022 MARCELA FRANQUEZ
Quality Review Completed 9/9/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 5/12/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 6/5/2023 MARCELA FRANQUEZ
Applicant returned to address corrections 6/23/2023 MARCELA FRANQUEZ
Plan Check Approved 7/25/2023 MARCELA FRANQUEZ
Issued 9/5/2023 APPLICANT
CofO in Progress 12/4/2024 BARRY HACHE
No Progress 12/7/2024 DEROLD HAUFF
CofO in Progress 12/7/2024 DEROLD HAUFF
Permit Finaled 12/15/2024 DEROLD HAUFF
CofO Issued 12/15/2024 DEROLD HAUFF
Permit Finaled 12/15/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/4/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/6/2022 CELINA MORENO
Sewer availability Cleared 10/6/2022 CELINA MORENO
Tenant Habitability Plan Cleared 12/14/2022 MICHAEL SOTO
SB8 RUD Cleared 2/16/2023 JESSICA WANG
Low Impact Development Cleared 2/21/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 2/21/2023 CELINA MORENO
Permit Cleared 4/28/2023 CINDY QI
Trees in Parkway Cleared 5/25/2023 ADALBERTO VERA

Contact Information

Contractor Sidekick Homes Llc; Lic. No.: 1098013-B       ,
Engineer Stevenson,, Mark Bevan; Lic. No.: C67499 10628 STRAWBERRY HILL LANE      WHITMORE LAKE, MI 48189

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/22/2023 Partial Inspection ANTHONY EGSON
Underground Mechanical 10/6/2023 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 10/20/2023 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 10/26/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 10/26/2023 Approved ANTHONY EGSON
Deputy Wood Construction 11/17/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Corrections Issued ANTHONY EGSON
Sewer 11/20/2023 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Partial Approval ANTHONY EGSON
Sewer 11/28/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/1/2023 Partial Approval ANTHONY EGSON
PLUMBING-Rough 12/19/2023 Partial Approval ANTHONY EGSON
PLUMBING-Rough 12/27/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 1/3/2024 Approved ANTHONY EGSON
HVAC-Rough 1/3/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 1/30/2024 Approved ANTHONY EGSON
Green Building Rough 1/30/2024 Approved ANTHONY EGSON
Verify Sprinkler Sign Off 1/30/2024 Approved ANTHONY EGSON
Insulation 2/26/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 2/26/2024 Approved ANTHONY EGSON
Drywall Nailing 2/29/2024 Partial Approval JOSH MEISTER
Drywall Nailing 3/12/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 3/12/2024 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 4/5/2024 No Access for Inspection JOSH MEISTER
Interior/Exterior Lathing 4/9/2024 Approved JOSH MEISTER
Gas Test 6/6/2024 Approved JOSH MEISTER
Underground Mechanical 6/6/2024 Not Ready for Inspection JOSH MEISTER
Underground Mechanical 6/10/2024 Partial Approval BRENDAN MORELLI
Final 6/24/2024 Corrections Issued ANTHONY EGSON
Green Building Final 6/24/2024 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Not Ready ANTHONY EGSON
Service/Power Release 6/24/2024 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 6/24/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 10/10/2024 Corrections Issued ANTHONY EGSON
HVAC-Final 10/10/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Final 10/10/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 10/22/2024 Corrections Issued BARRY HACHE
Final 10/22/2024 Not Ready for Inspection BARRY HACHE
Green Building Final 10/22/2024 Not Ready for Inspection BARRY HACHE
PLUMBING-Final 10/22/2024 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved BARRY HACHE
Service/Power Release 10/22/2024 Not Ready for Inspection BARRY HACHE
Smoke Detectors 10/22/2024 Approved BARRY HACHE
Final 10/30/2024 Conditional Approval MICHAEL LEWIS
Green Building Final 10/30/2024 Approved MICHAEL LEWIS
Service/Power Release 10/30/2024 Approved MICHAEL LEWIS
Final 12/3/2024 OK to Issue CofO BARRY HACHE
Service/Power Release 12/3/2024 Approved BARRY HACHE