645 1/2 W 85TH ST 90044

Certificate Information: 645 1/2 W 85TH ST 90044

Application / Permit
22010-10000-04090
Plan Check / Job No.
B22LA16315
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT (360 SQ FT) PER GCS 65852.2 (e) (1) (A).
Permit Issued
Issued on 11/3/2022
Issuing Office
Current Status
CofO Issued on 11/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2022 APPLICANT
Assigned to Plan Check Engineer 8/19/2022 ALEC MOUSAKHANIAN
Corrections Issued 8/20/2022 ALEC MOUSAKHANIAN
Plan Check Approved 10/5/2022 JEROME MAGAT PALMA
Plan Check Approved 11/1/2022 ALEC MOUSAKHANIAN
No Progress 11/1/2022 ALEC MOUSAKHANIAN
Plan Check Approved 11/2/2022 ALEC MOUSAKHANIAN
Issued 11/3/2022 APPLICANT
CofO in Progress 10/31/2023 MICHAEL LEWIS
CofO Issued 11/3/2023 DEROLD HAUFF
Permit Finaled 11/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/6/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 9/6/2022 JEANETTE VONG
Sewer availability Cleared 9/6/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/8/2022 JEANETTE VONG
Construction near power lines Cleared 9/27/2022 TINA MIRANDA
Hold Cleared 2/1/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/15/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 12/15/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 12/23/2022 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 2/15/2023 Partial Approval LILIANA PORTILLO
Underground Mechanical 2/23/2023 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 3/17/2023 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Corrections Issued LILIANA PORTILLO
Gas Test 3/17/2023 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 3/17/2023 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 3/17/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 3/17/2023 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 No Access for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 3/30/2023 No Access for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 4/4/2023 Approved STUART CHAPMAN
ELECTRICAL-Rough 4/20/2023 Corrections Issued LILIANA PORTILLO
Gas Test 4/20/2023 Approved LILIANA PORTILLO
HVAC-Rough 4/20/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 4/20/2023 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 4/25/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 4/25/2023 Approved LILIANA PORTILLO
HVAC-Rough 4/25/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 4/25/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/2/2023 Approved MICHAEL LEWIS
Insulation 5/2/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/2/2023 Approved MICHAEL LEWIS
Drywall Nailing 5/9/2023 Approved MICHAEL LEWIS
Special/Order Compliance 7/26/2023 Approved MICHAEL LEWIS
Service/Power Release 8/25/2023 Partial Inspection MICHAEL LEWIS
ELECTRICAL-Final 10/3/2023 Approved MICHAEL LEWIS
HVAC-Final 10/3/2023 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 10/3/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 10/16/2023 Approved JUSTIN HAWLEY
Final 10/16/2023 Corrections Issued JUSTIN HAWLEY
Green Building Final 10/16/2023 Approved JUSTIN HAWLEY
Green Building Rough 10/16/2023 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 10/16/2023 Approved JUSTIN HAWLEY
Final 10/30/2023 OK to Issue CofO MICHAEL LEWIS