522 W 92ND ST 90044

Certificate Information: 522 W 92ND ST 90044

Application / Permit
22010-10000-04074
Plan Check / Job No.
B22LA14898
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY S.F.D W/ ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 3/28/2023
Issuing Office
Current Status
CofO Issued on 10/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 CARLOS MONTES
Corrections Issued 8/13/2022 CARLOS MONTES
Quality Review Completed 8/17/2022 GARO TELMI
Plan Check Approved 10/17/2022 CARLOS MONTES
Issued 3/28/2023 APPLICANT
CofO in Progress 10/20/2023 JAMES CHAVEZ
Permit Finaled 10/23/2023 ANSON MAGLASANG
CofO Issued 10/23/2023 ANSON MAGLASANG
Permit Finaled 10/23/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 8/25/2022 STEVE MELGAR
Highway dedication Cleared 8/25/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/29/2022 STEVE MELGAR
Sewer availability Cleared 8/29/2022 STEVE MELGAR
Frnt yard landscape/Water mgmt Cleared 9/22/2022 CLAUDE GOODING
Low Impact Development Cleared 9/22/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 9/27/2022 STEVE MELGAR
Hydrant and Access approval Cleared 10/3/2022 MATTHEW CRAIG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/4/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 5/18/2023 Not Ready for Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval JAMES CHAVEZ
Underground Mechanical 5/22/2023 Partial Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/23/2023 Partial Approval JAMES CHAVEZ
Insulation 5/23/2023 Partial Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Partial Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Approved JAMES CHAVEZ
HVAC-Rough 7/27/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 7/27/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 7/28/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 7/28/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 7/28/2023 Approved JAMES CHAVEZ
Green Building Rough 7/28/2023 Approved JAMES CHAVEZ
MERV13>=Rough 7/28/2023 Approved JAMES CHAVEZ
Verify Sprinkler Sign Off 7/28/2023 Approved JAMES CHAVEZ
Insulation 7/31/2023 Approved JAMES CHAVEZ
Drywall Nailing 8/7/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 8/7/2023 Approved JAMES CHAVEZ
Underground Mechanical 8/28/2023 Partial Approval JAMES CHAVEZ
Underground Mechanical 9/5/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 9/19/2023 Partial Approval JOHN KLARIN
ELECTRICAL-Final 10/20/2023 Approved JAMES CHAVEZ
Final 10/20/2023 OK to Issue CofO JAMES CHAVEZ
Green Building Final 10/20/2023 Approved JAMES CHAVEZ
HVAC-Final 10/20/2023 Approved JAMES CHAVEZ
MERV13>=Final 10/20/2023 Approved JAMES CHAVEZ
PLUMBING-Final 10/20/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved JAMES CHAVEZ
Service/Power Release 10/20/2023 Approved JAMES CHAVEZ
Smoke Detectors 10/20/2023 Approved JAMES CHAVEZ
Service/Power Release 10/23/2023 Approved JAMES CHAVEZ