4951 N PETIT AVE 91436
Certificate Information: 4951 N PETIT AVE 91436
- Application / Permit
- 22010-10000-04050
- Plan Check / Job No.
- B22LA15218
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY ADU
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Current Status
- CofO Issued on 3/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/12/2022 | JOE VO |
| Corrections Issued | 8/14/2022 | JOE VO |
| Quality Review Completed | 8/15/2022 | GARO TELMI |
| Applicant returned to address corrections | 10/3/2022 | JOE VO |
| Plan Check Approved | 2/15/2023 | JOE VO |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 2/16/2024 | VINCENT HANLEY |
| CofO in Progress | 3/1/2024 | JOHN JANSON |
| Permit Finaled | 3/7/2024 | JOHN JANSON |
| CofO Issued | 3/7/2024 | JOHN JANSON |
| Permit Finaled | 3/7/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/29/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 10/29/2022 | RUEL COLE |
| Disturb/Remove Protected Trees | Cleared | 11/1/2022 | ADALBERTO VERA |
| Construction near power lines | Cleared | 11/4/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/15/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/15/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/29/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | -Unique Home Builders Inc; Lic. No.: 1083204-B | , |
| Contractor | Unique Home Builders Inc; Lic. No.: 1083204-B | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/9/2023 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/11/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Partial Approval | VINCENT HANLEY |
| Wood Frame | 4/24/2023 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/8/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2023 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 6/8/2023 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 6/8/2023 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 6/8/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/8/2023 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/15/2023 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/15/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/15/2023 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 6/15/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/15/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 6/15/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/15/2023 | Approved | VINCENT HANLEY |
| Wood Frame | 6/15/2023 | Approved | VINCENT HANLEY |
| Insulation | 6/22/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 7/28/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/28/2023 | Partial Approval | VINCENT HANLEY |
| Special/Order Compliance | 9/29/2023 | Corrections Issued | SEAN WIRCH |
| BUILDING-Rough-Frame | 12/14/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 12/14/2023 | Approved | VINCENT HANLEY |
| Final | 12/14/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 12/14/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 12/14/2023 | Approved | VINCENT HANLEY |
| HVAC-Final | 12/14/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 12/14/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 12/14/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 12/14/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 2/6/2024 | Corrections Issued | VINCENT HANLEY |
| Final | 2/6/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 2/6/2024 | Corrections Issued | VINCENT HANLEY |
| Final | 2/16/2024 | OK to Issue CofO | VINCENT HANLEY |
| Service/Power Release | 3/6/2024 | Approved | VINCENT HANLEY |