5917 N RHODES AVE 91607
Certificate Information: 5917 N RHODES AVE 91607
- Application / Permit
- 22010-10000-04038
- Plan Check / Job No.
- B22LA16096
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- Current Status
- CofO Issued on 8/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 9/8/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/19/2022 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 5/2/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 5/2/2023 | MAHNAZ NOURHASHEMI |
| Issued | 5/2/2023 | APPLICANT |
| CofO in Progress | 8/29/2024 | ROBERT GOLD |
| No Progress | 8/29/2024 | ROBERT GOLD |
| CofO in Progress | 8/29/2024 | ROBERT GOLD |
| CofO Issued | 8/30/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/30/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2022 | FERNANDO GIL |
| Hydrant and Access approval | Cleared | 11/18/2022 | LAVEON RIDER |
| Low Impact Development | Cleared | 12/23/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 2/22/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 2/23/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2023 | Approved | KIRK SANDERS |
| Deputy Steel/Welding | 9/25/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Corrections Issued | ROBERT GOLD |
| Deputy Wood Construction | 10/6/2023 | Conditional Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/16/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 12/4/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 12/4/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 12/8/2023 | Approved | JOSE AVILA |
| Deputy Wood Construction | 12/12/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/18/2023 | Approved | JOSE AVILA |
| Green Building Rough | 12/18/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/18/2023 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 12/18/2023 | Approved | JOSE AVILA |
| Insulation | 12/26/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/26/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/26/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 1/2/2024 | Approved | CHRISTOPHER ROJAS |
| Sewer | 1/18/2024 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 1/18/2024 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 3/14/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 5/24/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 7/3/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 7/12/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Service/Power Release | 7/12/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/12/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 7/18/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 7/18/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 8/27/2024 | OK to Issue CofO | LOUIS ESCOTO |