4218 S REDWOOD AVE 90066

Certificate Information: 4218 S REDWOOD AVE 90066

Application / Permit
22010-10000-04032
Plan Check / Job No.
B22LA16076
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 22'-1" X 17'-11" ONE STORY ACCESORY DWELLING UNIT WITH ROOF DECK PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 6/28/2023
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 9/6/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/13/2022 OMID HEDAYAT
Applicant returned to address corrections 4/26/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 5/18/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 6/8/2023 SEWADA ZADOORAN MILAGARDI
No Progress 6/23/2023 SEWADA ZADOORAN MILAGARDI
Plan Check Approved 6/23/2023 SEWADA ZADOORAN MILAGARDI
No Progress 6/23/2023 SEWADA ZADOORAN MILAGARDI
Plan Check Approved 6/23/2023 SEWADA ZADOORAN MILAGARDI
Issued 6/28/2023 APPLICANT
Permit Finaled 4/24/2025 RICHARD STEINBACH
CofO Issued 4/24/2025 RICHARD STEINBACH
Permit Finaled 4/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/22/2022 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/26/2022 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/26/2022 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 10/21/2022 KURT CORRAL
Construction near power lines Cleared 11/30/2022 RIDWAN HARDY
Construction within easement Cleared 11/30/2022 RIDWAN HARDY
Low Impact Development Cleared 1/24/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 2/16/2023 HISASHI KOBAYAKAWA

Contact Information

Contractor Westside Construction; Lic. No.: 852976-B       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/14/2023 Partial Inspection HERBERT GIRON
Underground Mechanical 10/13/2023 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/20/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 10/20/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/22/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/26/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/3/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 7/25/2024 Approved JESUS RODRIGUEZ
Sewer 7/25/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 7/25/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 8/5/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 8/5/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/27/2024 Approved JESUS PINEDA
Green Building Rough 8/27/2024 Approved JESUS PINEDA
HVAC-Rough 8/27/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 8/27/2024 Partial Approval JESUS PINEDA
Verify Sprinkler Sign Off 8/27/2024 Approved JESUS PINEDA
Insulation 9/4/2024 Corrections Issued JESUS PINEDA
Drywall Nailing 9/13/2024 Approved JESUS PINEDA
Insulation 9/13/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 10/16/2024 Approved JESUS PINEDA
Shower Pan 10/16/2024 Approved JESUS PINEDA
ELECTRICAL-Final 1/28/2025 Approved JESUS PINEDA
HVAC-Final 1/31/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 1/31/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 2/4/2025 Approved MICHAEL ALLEN
Service/Power Release 2/4/2025 Approved MICHAEL ALLEN
HVAC-Final 2/7/2025 Approved BOBBY KEY
Final 3/11/2025 Partial Approval MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 3/11/2025 SGSOV Not Required MICHAEL ALLEN
Smoke Detectors 3/11/2025 Approved MICHAEL ALLEN