1161 N STONE ST 90063
Certificate Information: 1161 N STONE ST 90063
- Application / Permit
- 22010-10000-04014
- Plan Check / Job No.
- B22LA15984
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 800 SQ FT (25' X 32') ADU (1-STORY)
- Permit Issued
- Issued on 12/22/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | NGHI SU |
| Corrections Issued | 9/2/2022 | NGHI SU |
| Quality Review Completed | 9/2/2022 | FARUK SEZER |
| Building Plans Picked Up | 9/6/2022 | APPLICANT |
| Applicant returned to address corrections | 10/14/2022 | NGHI SU |
| Plan Check Approved | 12/22/2023 | NGHI SU |
| Issued | 12/22/2023 | APPLICANT |
| CofO in Progress | 6/13/2025 | ALIZAH MAYAGOITIA |
| No Progress | 6/14/2025 | DEROLD HAUFF |
| CofO in Progress | 6/14/2025 | DEROLD HAUFF |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
| CofO Issued | 6/17/2025 | DEROLD HAUFF |
| Permit Finaled | 6/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 9/17/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 9/17/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 9/17/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 9/17/2022 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 9/17/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 10/3/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 12/13/2023 | JEANIE LAM |
| GPI Written Notices | Cleared | 12/22/2023 | NGHI SU |
| Grading Pre-Inspection | Cleared | 12/22/2023 | NGHI SU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bartelle,, Kristofer Grimm; Lic. No.: C84617 | 19900 ACRE ST LOS ANGELES, CA 91324 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/18/2024 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/20/2024 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/3/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/22/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/24/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 5/29/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 6/11/2024 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 6/11/2024 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/17/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 6/17/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Partial Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 8/13/2024 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Rough | 10/9/2024 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 10/15/2024 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 10/21/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/21/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/30/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/30/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/30/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/18/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/18/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 11/18/2024 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 11/18/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 11/22/2024 | Approved | JOSH MEISTER |
| Underground Mechanical | 11/22/2024 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 12/23/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 1/16/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 4/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/27/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 5/27/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 5/27/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 5/27/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 5/27/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 5/27/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/12/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/12/2025 | Approved | ALIZAH MAYAGOITIA |