3109 S VINEYARD AVE 90016
Certificate Information: 3109 S VINEYARD AVE 90016
- Application / Permit
- 22010-10000-03980
- Plan Check / Job No.
- B22LA15858
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. (N) ADU ADDITION TO (E) DETACHED GARAGE
- Permit Issued
- Issued on 9/11/2023
- Issuing Office
- Current Status
- CofO Issued on 1/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2022 | FERNANDO FLORES |
| Corrections Issued | 8/23/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 11/15/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 8/29/2023 | GEORGE ALVAREZ |
| Plan Check Approved | 9/9/2023 | FERNANDO FLORES |
| Issued | 9/11/2023 | APPLICANT |
| CofO in Progress | 1/23/2025 | JUSTIN HAWLEY |
| Permit Finaled | 1/28/2025 | DEROLD HAUFF |
| CofO Issued | 1/28/2025 | DEROLD HAUFF |
| Permit Finaled | 1/28/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2023 | AMAAN MALIK |
| Construction near power lines | Cleared | 6/7/2023 | RIDWAN HARDY |
| Flood clearance | Cleared | 7/31/2023 | SAMSON WONG |
| Low Impact Development | Cleared | 8/18/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/26/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 8/26/2023 | CHRISTOPHER ROCHA |
Contact Information
| Architect | Shum,, Simon Tak-Wong; Lic. No.: C22647 | 1933 PASEO LA PAZ POMONA, CA 91768 |
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 10/12/2023 | Approved | CALEB MEISTER |
| Footing/Foundation/Slab | 10/12/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 10/26/2023 | Approved | CALEB MEISTER |
| Insulation | 10/31/2023 | Partial Approval | CALEB MEISTER |
| FLOOD-Proofing Certificate | 11/13/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/13/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/21/2023 | Partial Approval | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 1/18/2024 | Corrections Issued | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 1/18/2024 | Approved | JUSTIN HAWLEY |
| FLOOD-Proofing Certificate | 1/18/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Rough | 1/18/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Rough | 1/18/2024 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 1/18/2024 | Corrections Issued | JUSTIN HAWLEY |
| Underground Mechanical | 1/18/2024 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/24/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| FLOOD-Proofing Certificate | 1/24/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Gas Test | 1/24/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/24/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 1/24/2024 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 2/8/2024 | Approved | JUSTIN HAWLEY |
| FLOOD-Proofing Certificate | 2/8/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 2/8/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 2/8/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 2/8/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 2/8/2024 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 2/16/2024 | Approved | JUSTIN HAWLEY |
| Shower Pan | 2/16/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 3/28/2024 | Approved | JUSTIN HAWLEY |
| Final | 9/9/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 9/9/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 9/9/2024 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 9/9/2024 | Approved | JUSTIN HAWLEY |
| Final | 10/8/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 10/8/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Final | 10/15/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Final | 10/15/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 1/22/2025 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 1/22/2025 | Approved | JUSTIN HAWLEY |
| Final | 1/23/2025 | OK to Issue CofO | JUSTIN HAWLEY |
| Service/Power Release | 1/23/2025 | Approved | JUSTIN HAWLEY |