3919 3/4 W BOYCE AVE 90039

Certificate Information: 3919 3/4 W BOYCE AVE 90039

Application / Permit
22010-10000-03978
Plan Check / Job No.
B22LA26788
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New 1-story deatached accessory dwelling unit (ADU) per Govt Code 65852.2(e)(1)(B).
Permit Issued
Issued on 2/7/2023
Issuing Office
Current Status
CofO Issued on 2/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2023 APPLICANT
Assigned to Plan Check Engineer 1/4/2023 TU HUA
Plan Check Approved 1/6/2023 TU HUA
No Progress 1/30/2023 TU HUA
Plan Check Approved 1/30/2023 TU HUA
Issued 2/7/2023 APPLICANT
CofO in Progress 2/8/2024 ALIZAH MAYAGOITIA
Permit Finaled 2/12/2024 DEROLD HAUFF
CofO Issued 2/12/2024 DEROLD HAUFF
Permit Finaled 2/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/24/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/29/2022 WALLIE JONG
Sewer availability Cleared 8/29/2022 WALLIE JONG
ZI Cleared 9/29/2022 LOUIS ORTEGA
Construction near power lines Cleared 10/29/2022 RIDWAN HARDY
Low Impact Development Cleared 12/22/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/30/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/25/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 3/25/2023 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 3/30/2023 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/4/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Inspection HAMIK HARTOUNIAN
Shower Pan 7/5/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/13/2023 Partial Approval HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 9/13/2023 Approved HAMIK HARTOUNIAN
Insulation 9/18/2023 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 9/18/2023 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 9/22/2023 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 9/22/2023 Approved HAMIK HARTOUNIAN
Green Building Rough 9/22/2023 Approved HAMIK HARTOUNIAN
Insulation 9/22/2023 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 9/22/2023 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/2/2023 Approved JOSH MEISTER
BUILDING-Rough-Frame 2/1/2024 Approved HAMIK HARTOUNIAN
Final 2/1/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/1/2024 Approved HAMIK HARTOUNIAN
Green Building Final 2/1/2024 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 2/1/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 2/1/2024 Approved HAMIK HARTOUNIAN
Final 2/6/2024 Conditional Approval ALIZAH MAYAGOITIA
Service/Power Release 2/6/2024 Approved ALIZAH MAYAGOITIA
Final 2/8/2024 OK to Issue CofO ALIZAH MAYAGOITIA