21138 S HALLDALE AVE 90501
Certificate Information: 21138 S HALLDALE AVE 90501
- Application / Permit
- 22010-10000-03972
- Plan Check / Job No.
- B22LA15833
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert existing garage to new ADU 1,131 sq.ft. gcs 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | DANIEL SANJUAN |
| Corrections Issued | 8/12/2022 | DANIEL SANJUAN |
| Plan Check Approved | 10/24/2022 | STANLEY RAAP |
| Issued | 10/28/2022 | APPLICANT |
| CofO in Progress | 8/16/2023 | EUGENE CASSIDY |
| CofO Issued | 8/16/2023 | ANSON MAGLASANG |
| Permit Finaled | 8/16/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2022 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | HUGO LOPEZ |
| Sewer availability | Cleared | 9/29/2022 | HUGO LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tagudar,, Fred; Lic. No.: NA33612 | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/18/2022 | Approved | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 12/27/2022 | Approved | JOHN KLARIN |
| Deputy Drilled-In Anchors | 12/28/2022 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2023 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/5/2023 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/19/2023 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 1/31/2023 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/23/2023 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/13/2023 | Approved | EUGENE CASSIDY |
| Final | 6/13/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 6/13/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 6/13/2023 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/13/2023 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 6/13/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/11/2023 | Approved | EUGENE CASSIDY |
| Final | 7/11/2023 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 7/11/2023 | Approved | EUGENE CASSIDY |
| HVAC-Final | 7/11/2023 | Approved | EUGENE CASSIDY |