1538 W 30TH ST 90007
Certificate Information: 1538 W 30TH ST 90007
- Application / Permit
- 22010-10000-03970
- Plan Check / Job No.
- B22LA15818
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN: CONVERT 26' X 34' 10" IRR.-SHAPE PORTION OF (E) 3-CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e), CONVERT 15' 2" X 19' 8" PORTION OF 3-CAR GARAGE TO PATIO COVER, REMODEL LAUNDRY OF (E) APARTMENT BUILDING, CONVERT 5' 10" X 1' 9" PORTION OF LAUNDRY TO ADU AND 5' 10" X 8' PORTION OF STORAGE TO ADU . ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/10/2023
- Issuing Office
- Current Status
- CofO Issued on 8/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 8/30/2022 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 9/28/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/20/2022 | GURUNATH NESARAJAH |
| Issued | 4/10/2023 | APPLICANT |
| CofO in Progress | 8/14/2023 | MARTIN TAVITIAN |
| Permit Finaled | 8/14/2023 | ERNESTO CORRAL |
| CofO Issued | 8/14/2023 | ERNESTO CORRAL |
| Permit Finaled | 8/14/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 9/7/2022 | AMAAN MALIK |
| Tenant Habitability Plan | Cleared | 9/13/2022 | MICHAEL SOTO |
| "Q" conditions | Cleared | 10/4/2022 | JAZMIN ROQUE |
| ZI | Cleared | 10/4/2022 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2022 | AMAAN MALIK |
Contact Information
| Contractor | Fort Multifamily Inc; Lic. No.: 1097435-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/3/2023 | Conditional Approval | ALAN MORELOS |
| Green Building Rough | 5/4/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Interior/Exterior Lathing | 5/4/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| METHANE-Rough | 5/4/2023 | Not Ready for Inspection | VAHE KELEDJIAN |
| Pre-Inspection | 5/4/2023 | Partial Inspection | VAHE KELEDJIAN |
| Deputy Wood Construction | 5/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Interior/Exterior Lathing | 5/19/2023 | Approved | MARTIN TAVITIAN |
| METHANE-Rough | 5/19/2023 | Approved | MARTIN TAVITIAN |
| Wood Frame | 5/19/2023 | Approved | MARTIN TAVITIAN |
| Insulation | 5/25/2023 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 5/30/2023 | Approved | MARTIN TAVITIAN |
| Final | 7/3/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 7/3/2023 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 7/3/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 7/14/2023 | Partial Approval | MARTIN TAVITIAN |
| Green Building Final | 7/14/2023 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 7/14/2023 | Approved | MARTIN TAVITIAN |
| Verify Rec and Parks Fee Memo | 7/14/2023 | Approved | MARTIN TAVITIAN |