6219 W 96TH ST 90045
Certificate Information: 6219 W 96TH ST 90045
- Application / Permit
- 22010-10000-03961
- Plan Check / Job No.
- B22LA15745
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- **ePlan**LAX** NEW ATSAC HUB -- NEW PREFABRICATED UNMANNED ENCLOSURE TO HOUSE SIGNAL LIGHT TRAFFIC COMPUTER SYSTEMS. SEE COMMENTS.
- Permit Issued
- Issued on 6/2/2025
- Issuing Office
- Current Status
- Issued on 6/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | EDUARDO RODRIGUEZ |
| Corrections Issued | 9/9/2022 | EDUARDO RODRIGUEZ |
| Quality Review Completed | 9/12/2022 | LIPING TENG |
| Applicant returned to address corrections | 10/11/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 11/1/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 11/3/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 11/7/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 11/28/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 12/7/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 8/28/2023 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 11/20/2023 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 5/13/2025 | EDUARDO RODRIGUEZ |
| Issued | 6/2/2025 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 9/1/2022 | Lily Teng |
| Project Permit | Cleared | 9/14/2022 | EDUARDO RODRIGUEZ |
| Specific Plan | Cleared | 10/4/2022 | ROBERT SANCHEZ |
| Address approval | Cleared | 11/5/2022 | SAUL GARCIA |
| Highway dedication | Cleared | 11/5/2022 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 11/5/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 11/5/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 11/5/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2022 | SAUL GARCIA |
| Tract Map conditions | Cleared | 11/7/2022 | LOUIS ORTEGA |
| Tract Map conditions | Cleared | 11/7/2022 | LOUIS ORTEGA |
| Tract Map conditions | Cleared | 11/7/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 11/7/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 11/7/2022 | LOUIS ORTEGA |
| Low Impact Development | Cleared | 11/10/2022 | AMMAR ELTAWIL |
| DAS Clearance | Cleared | 11/16/2022 | Lily Teng |
| Airport buildings | Cleared | 11/18/2022 | DOMINIQUE MEDINA |
| City owned building/parcel | Cleared | 12/8/2022 | EDUARDO RODRIGUEZ |
| Hydrant and Access approval | Cleared | 12/22/2022 | JOHN CONNEALLY |
Contact Information
| Architect | Leckie,, David Pentland; Lic. No.: C9183 | 14348 RIVERSIDE DRIVE # 6 SHERMAN OAKS, CA 91423 |
| Contractor | Aldridge Electric Inc; Lic. No.: 855841-A | 844 E ROCKLAND RD LIBERTYVILLE, IL 60048 |
| Engineer | Kirby,, Anthony David; Lic. No.: C79357 | 30836 OVERFALL DR WESTLAKE VILLAGE, CA 91362 |
| Engineer | Noll,, Patrick; Lic. No.: S6374 | 900 WILSHIRE BLVD 19TH FLOOR LOS ANGELES, CA 90017 |
Inspector Information
| NICK LAROCCA, (213) 473-2153 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/18/2025 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 11/18/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Deputy Reinf. Concrete | 2/18/2026 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/19/2026 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 2/20/2026 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 2/23/2026 | Partial Approval | VASIL MIHALEV |
| Deputy Reinf. Concrete | 2/24/2026 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 2/27/2026 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 2/27/2026 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Concrete | 3/2/2026 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 3/3/2026 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 4/6/2026 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 4/8/2026 | Approved | NICK LAROCCA |
| Deputy Drilled-In Anchors | 4/9/2026 | Approved | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 4/9/2026 | Approved | NICK LAROCCA |
| Final | 4/9/2026 | Not Ready for Inspection | NICK LAROCCA |
| Footing/Foundation/Slab | 4/9/2026 | Approved | NICK LAROCCA |
| Green Building Final | 4/9/2026 | Approved | NICK LAROCCA |
| Green Building Rough | 4/9/2026 | Approved | NICK LAROCCA |
| Masonry Wall/Backfill | 4/9/2026 | Not Ready for Inspection | NICK LAROCCA |
| Notice of Violation | 4/9/2026 | Not Required | NICK LAROCCA |
| Order to Comply | 4/9/2026 | Not Required | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Approved | NICK LAROCCA |
| Smoke Detectors | 4/9/2026 | Approved | NICK LAROCCA |
| Verify Sprinkler Sign Off | 4/9/2026 | Approved | NICK LAROCCA |
| Wall Anchors | 4/9/2026 | Approved | NICK LAROCCA |
| Wood Frame | 4/9/2026 | Approved | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 5/4/2026 | Partial Approval | NICK LAROCCA |