5457 S 10TH AVE 90043

Certificate Information: 5457 S 10TH AVE 90043

Application / Permit
22010-10000-03940
Plan Check / Job No.
B22LA15614
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ACCESSORY BUILDING INCLUDES ADU OVER ATTACHED GARAGE/STORAGE. "COMPLY WITH DEPARTMENT ORDER effective date 06/08/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 953384. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 5/3/2023
Issuing Office
Metro
Current Status
Issued on 5/3/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/5/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 JAD BASMA
Corrections Issued 8/21/2022 JAD BASMA
Quality Review Completed 8/24/2022 KEN GILL
Building Plans Picked Up 9/2/2022 APPLICANT
Applicant returned to address corrections 2/13/2023 JAD BASMA
Plan Check Approved 4/28/2023 JAD BASMA
Issued 5/3/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/20/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 9/20/2022 AMAAN MALIK
Sewer availability Cleared 9/20/2022 AMAAN MALIK
Hydrant and Access approval Cleared 10/14/2022 LAVEON RIDER
Roof/Waste drainage to street Cleared 3/7/2023 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/28/2023 Corrections Issued JOHN PARKER
ELECTRICAL-Rough 12/19/2023 Approved JOHN PARKER
Footing/Foundation/Slab 12/19/2023 Corrections Issued JOHN PARKER
Insulation 12/19/2023 Approved JOHN PARKER
BUILDING-Rough-Frame 5/14/2024 No Access for Inspection JOHN PARKER
Footing/Foundation/Slab 5/14/2024 No Access for Inspection JOHN PARKER
Green Building Rough 5/14/2024 No Access for Inspection JOHN PARKER
Deputy Drilled-In Anchors 5/17/2024 Approved JOHN PARKER
Footing/Foundation/Slab 6/24/2024 Approved JOHN PARKER
Reinforced Concrete Frame 7/8/2024 Approved JOHN PARKER
Deputy Drilled-In Anchors 8/30/2024 Approved JOHN PARKER
ELECTRICAL-Rough 12/24/2024 Approved JOHN PARKER
PLUMBING-Rough 12/24/2024 Approved JOHN PARKER
Wood Frame 12/24/2024 Approved JOHN PARKER
BUILDING-Rough-Frame 4/25/2025 Approved JOHN PARKER
ELECTRICAL-Final 4/25/2025 Corrections Issued JOHN PARKER
Final 4/25/2025 Not Ready for Inspection JOHN PARKER
Green Building Final 4/25/2025 Approved JOHN PARKER
Green Building Rough 4/25/2025 Approved JOHN PARKER
HVAC-Final 4/25/2025 Corrections Issued JOHN PARKER
PLUMBING-Final 4/25/2025 Not Ready for Inspection JOHN PARKER
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Approved JOHN PARKER
Smoke Detectors 4/25/2025 Not Ready for Inspection JOHN PARKER
ELECTRICAL-Final 7/3/2025 Approved JOHN PARKER
Final 7/3/2025 Partial Approval JOHN PARKER
HVAC-Final 7/3/2025 Approved JOHN PARKER
PLUMBING-Final 7/3/2025 Approved JOHN PARKER
Smoke Detectors 7/3/2025 Approved JOHN PARKER