2125-2125 1/2 S 2ND AVE 90018
Certificate Information: 2125-2125 1/2 S 2ND AVE 90018
- Application / Permit
- 22010-10000-03928
- Plan Check / Job No.
- B22LA15574
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan NEW 2 STORY two ADUs with attached garage
- Permit Issued
- Issued on 1/14/2024
- Issuing Office
- Current Status
- CofO Issued on 10/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 9/20/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 9/21/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/1/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/8/2024 | ARSALAN SHABESTARI |
| Issued | 1/14/2024 | APPLICANT |
| CofO in Progress | 10/17/2025 | JUSTIN HAWLEY |
| No Progress | 10/23/2025 | DEROLD HAUFF |
| CofO in Progress | 10/23/2025 | DEROLD HAUFF |
| Permit Finaled | 10/24/2025 | DEROLD HAUFF |
| CofO Issued | 10/24/2025 | DEROLD HAUFF |
| Permit Finaled | 10/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/12/2022 | GILBERT URREA |
| Address approval | Cleared | 11/29/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/2/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 1/19/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 1/19/2023 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 1/23/2023 | KYLE WINSTON |
| Low Impact Development | Cleared | 2/15/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/23/2023 | AMAAN MALIK |
Contact Information
| Contractor | Aten Enterprises; Lic. No.: 782418-B | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2024 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Barrier | 1/26/2024 | Not Ready for Inspection | EDWIN GREGORYONA |
| METHANE-Subgrade | 1/26/2024 | Not Ready for Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 1/31/2024 | Corrections Issued | ALFREDO LOPEZ |
| METHANE-Barrier | 1/31/2024 | Approved | ALFREDO LOPEZ |
| METHANE-Subgrade | 1/31/2024 | Approved | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 2/13/2024 | Conditional Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 2/14/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Rough | 3/7/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Verify Sprinkler Sign Off | 3/7/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 3/7/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| Deputy Steel/Welding | 4/2/2024 | Conditional Approval | DARRYL ARNOLD |
| METHANE-Rough | 4/3/2024 | Not Ready for Inspection | JACOB MYERS |
| Verify Sprinkler Sign Off | 4/3/2024 | Not Ready for Inspection | JACOB MYERS |
| Wood Frame | 4/3/2024 | Corrections Issued | JACOB MYERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2024 | Partial Approval | JACOB MYERS |
| METHANE-Rough | 4/5/2024 | Not Ready for Inspection | JACOB MYERS |
| Verify Sprinkler Sign Off | 4/5/2024 | Not Ready for Inspection | JACOB MYERS |
| METHANE-Rough | 4/12/2024 | Approved | RONALD JIMENEZ |
| Verify Sprinkler Sign Off | 4/12/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 4/12/2024 | Corrections Issued | RONALD JIMENEZ |
| Special/Order Compliance | 5/20/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Pre-Inspection | 5/23/2024 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 5/28/2024 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | JUSTIN HAWLEY |
| Wood Frame | 5/28/2024 | Approved | JUSTIN HAWLEY |
| Insulation | 6/3/2024 | Approved | JUSTIN HAWLEY |
| Special/Order Compliance | 6/3/2024 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 6/10/2024 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 6/27/2024 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 7/23/2024 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 9/27/2024 | Approved | JUSTIN HAWLEY |
| Final | 1/21/2025 | No Access for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 1/21/2025 | No Access for Inspection | JUSTIN HAWLEY |
| Pre-Inspection | 1/23/2025 | Corrections Issued | JUSTIN HAWLEY |
| Final | 9/26/2025 | Corrections Issued | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 9/26/2025 | Approved | JUSTIN HAWLEY |
| Final | 10/14/2025 | Corrections Issued | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Approved | JUSTIN HAWLEY |
| Final | 10/17/2025 | OK to Issue CofO | JUSTIN HAWLEY |