1349 N MOHAWK ST 90026
Certificate Information: 1349 N MOHAWK ST 90026
- Application / Permit
- 22010-10000-03911
- Plan Check / Job No.
- B22LA15510
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Existing Detached Garage converted to New ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Current Status
- CofO Issued on 3/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 8/25/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 9/8/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 9/21/2022 | LAWRENCE QUIRANTE |
| Plan Check Approved | 9/24/2022 | SAMUEL GONZALEZ |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 3/18/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
| CofO Issued | 3/20/2025 | DEROLD HAUFF |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/31/2022 | ISMAEL HERNANDEZ |
| Address approval | Cleared | 9/3/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 9/3/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kang,, Joshua Yj; Lic. No.: C63216 | 35 SPARROWHAWK IRVINE, CA 92604 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/4/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/16/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 2/17/2023 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/23/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/23/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 2/23/2023 | Corrections Issued | STUART CHAPMAN |
| Sewer | 2/23/2023 | Approved | STUART CHAPMAN |
| Underground Mechanical | 2/23/2023 | Approved | STUART CHAPMAN |
| Insulation | 3/9/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 3/22/2023 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/22/2023 | Approved | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 3/29/2023 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/30/2023 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 3/30/2023 | Partial Approval | THOMAS LOGRASSO |
| Insulation | 3/30/2023 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/4/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/4/2023 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 4/17/2023 | Approved | KATHRYN BUTTERWORTH |
| Final | 9/19/2023 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 9/19/2023 | Approved | THOMAS LOGRASSO |
| Final | 2/14/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 4/4/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 1/13/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 1/13/2025 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Final | 2/13/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 2/28/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 3/14/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |