1720 1/2 E 112TH ST 90059

Certificate Information: 1720 1/2 E 112TH ST 90059

Application / Permit
22010-10000-03904
Plan Check / Job No.
B22LA15479
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY ADU PER STATE LAW
Permit Issued
Issued on 6/2/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2022 APPLICANT
Assigned to Plan Check Engineer 8/8/2022 KHUONG TRUONG
Corrections Issued 8/9/2022 KHUONG TRUONG
Applicant returned to address corrections 5/12/2023 SAMUEL GONZALEZ
Plan Check Approved 5/15/2023 WEIJIAN HUANG
Issued 6/2/2023 APPLICANT
CofO in Progress 2/21/2024 JAMES CHAVEZ
CofO Issued 2/22/2024 ANSON MAGLASANG
Permit Finaled 2/22/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/19/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/11/2023 WALLIE JONG
Sewer availability Cleared 4/13/2023 WALLIE JONG
Low Impact Development Cleared 5/5/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/10/2023 ADRIAN SANCHEZ

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/5/2023 Partial Approval JAMES CHAVEZ
Footing/Foundation/Slab 6/12/2023 Order to Comply Issued JOHN KLARIN
BUILDING-Rough-Frame 7/6/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 7/6/2023 Approved JOHN KLARIN
Green Building Rough 7/6/2023 Approved JOHN KLARIN
HVAC-Rough 7/6/2023 Approved JOHN KLARIN
PLUMBING-Rough 7/6/2023 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 7/6/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 7/6/2023 Approved JOHN KLARIN
Insulation 7/10/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 7/10/2023 Approved JOHN KLARIN
Drywall Nailing 7/17/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 7/17/2023 Approved JOHN KLARIN
Shower Pan 7/17/2023 Approved JOHN KLARIN
ELECTRICAL-Final 12/1/2023 Approved JAMES CHAVEZ
Final 12/1/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 12/1/2023 Approved JAMES CHAVEZ
Green Building Final 12/1/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Final 12/1/2023 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Final 12/1/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Approved JAMES CHAVEZ
Service/Power Release 12/1/2023 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 12/1/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 1/3/2024 Approved JOHN KLARIN
Final 1/3/2024 Corrections Issued JOHN KLARIN
Green Building Final 1/3/2024 Approved JOHN KLARIN
HVAC-Final 1/3/2024 Approved JOHN KLARIN
PLUMBING-Final 1/3/2024 Approved JOHN KLARIN
Service/Power Release 1/3/2024 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 2/14/2024 Approved JAMES CHAVEZ
Final 2/14/2024 OK to Issue CofO JAMES CHAVEZ
HVAC-Final 2/14/2024 Approved JAMES CHAVEZ
PLUMBING-Final 2/14/2024 Approved JAMES CHAVEZ
Service/Power Release 2/14/2024 Approved JAMES CHAVEZ
Service/Power Release 2/22/2024 Approved JAMES CHAVEZ