2419 E 3RD ST 1-2 90033

Certificate Information: 2419 E 3RD ST 1-2 90033

Application / Permit
22010-10000-03894
Plan Check / Job No.
B22LA15432
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW THREE STORY DUPLEX. AT FRONT OF LOT.
Permit Issued
Issued on 6/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 TSE MING HUANG
Corrections Issued 8/25/2022 TSE MING HUANG
Quality Review Completed 8/31/2022 KEN GILL
Building Plans Picked Up 9/7/2022 APPLICANT
Applicant returned to address corrections 1/18/2023 TSE MING HUANG
Plan Check Approved 2/2/2023 TSE MING HUANG
Issued 6/7/2023 APPLICANT
CofO in Progress 9/19/2025 FREDDIE RIVERA
Permit Finaled 9/21/2025 DEROLD HAUFF
CofO Issued 9/21/2025 DEROLD HAUFF
Permit Finaled 9/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/6/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/11/2022 WALLIE JONG
Sewer availability Cleared 10/11/2022 WALLIE JONG
Clean Up Green Up Cleared 10/17/2022 CLAUDE GOODING
Roof/Waste drainage to street Cleared 11/18/2022 WALLIE JONG
Hydrant and Access approval Cleared 1/9/2023 GILBERT URREA
Grading Pre-Inspection Cleared 2/2/2023 TSE MING HUANG

Contact Information

Contractor Rios William A; Lic. No.: 866335-B P O BOX 1061      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 12/14/2023 Partial Approval FREDDIE RIVERA
METHANE-Rough 12/14/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 12/18/2023 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 1/11/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval JUSTIN HAWLEY
Deputy Wood Construction 6/3/2024 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Approved FREDDIE RIVERA
ELECTRICAL-Rough 8/7/2024 Approved FREDDIE RIVERA
HVAC-Rough 8/7/2024 Not Ready for Inspection FREDDIE RIVERA
METHANE-Rough 8/7/2024 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 8/7/2024 Corrections Issued FREDDIE RIVERA
Wood Frame 8/7/2024 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 8/30/2024 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 8/30/2024 Partial Approval FREDDIE RIVERA
Wood Frame 9/9/2024 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 9/11/2024 Conditional Approval FREDDIE RIVERA
Green Building Rough 9/11/2024 Approved FREDDIE RIVERA
METHANE-Rough 9/11/2024 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 9/11/2024 Approved FREDDIE RIVERA
Insulation 10/1/2024 Approved FREDDIE RIVERA
Drywall Nailing 10/17/2024 Partial Inspection FREDDIE RIVERA
Drywall Nailing 10/22/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 9/4/2025 Approved FREDDIE RIVERA
Final 9/4/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 9/4/2025 Approved FREDDIE RIVERA
Green Building Final 9/4/2025 Approved FREDDIE RIVERA
METHANE-Barrier 9/4/2025 Approved FREDDIE RIVERA
METHANE-Subgrade 9/4/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/4/2025 SGSOV Approved FREDDIE RIVERA
Service/Power Release 9/4/2025 Partial Inspection FREDDIE RIVERA
Smoke Detectors 9/4/2025 Approved FREDDIE RIVERA
Service/Power Release 9/9/2025 Conditional Approval FREDDIE RIVERA
Final 9/11/2025 Partial Inspection FREDDIE RIVERA
Final 9/19/2025 OK to Issue CofO FREDDIE RIVERA
Service/Power Release 9/19/2025 Approved FREDDIE RIVERA