515-515 1/2 W 88TH ST 90044

Certificate Information: 515-515 1/2 W 88TH ST 90044

Application / Permit
22010-10000-03850
Plan Check / Job No.
B22LA15222
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
*eplan* PROPOSED ADDITION AND CONVERSION OF (E) 1-STORY SFD TO A 2-STORY DUPLEX. *** BUILDING TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGHOUT*** 1 of 2
Permit Issued
Issued on 8/22/2024
Issuing Office
Current Status
Issued on 8/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/2/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 CRYSTEL MAALOUF
Corrections Issued 9/18/2022 ADRIANA LOPEZ
Quality Review Completed 9/20/2022 GARO TELMI
Applicant returned to address corrections 5/2/2024 ADRIANA LOPEZ
Applicant returned to address corrections 7/18/2024 ADRIANA LOPEZ
Applicant returned to address corrections 8/15/2024 ADRIANA LOPEZ
Plan Check Approved 8/22/2024 CRYSTEL MAALOUF
Plan Check Approved 8/22/2024 CRYSTEL MAALOUF
Issued 8/22/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/8/2023 CELINA MORENO
Frnt yard landscape/Water mgmt Cleared 5/9/2023 MAYELA VILLA
Hydrant and Access approval Cleared 5/19/2023 LAVEON RIDER
Low Impact Development Cleared 9/28/2023 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 10/3/2023 CELINA MORENO
Roof/Waste drainage to street Cleared 10/3/2023 CELINA MORENO
Sewer availability Cleared 10/3/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/25/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 9/25/2024 Not Ready for Inspection MICHAEL LEWIS
PLUMBING-Rough 9/25/2024 Not Ready for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 9/27/2024 Partial Inspection MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/16/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/16/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Approved JOSE MACIAS
PLUMBING-Rough 11/12/2024 Approved JOSE MACIAS
Insulation 11/15/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval JOHN QUINTANILLA
Wood Frame 12/16/2024 Not Ready for Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Conditional Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Corrections Issued JOHN QUINTANILLA
Deputy Wood Construction 6/17/2025 Conditional Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 7/8/2025 Approved RONNIE MEDINA
HVAC-Rough 7/11/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 7/11/2025 Approved JOHN QUINTANILLA
Wood Frame 7/11/2025 Not Ready for Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 7/18/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 7/18/2025 Approved JOHN QUINTANILLA
Green Building Rough 7/18/2025 Approved JOHN QUINTANILLA
MERV13>=Rough 7/18/2025 Not Ready for Inspection JOHN QUINTANILLA
Wood Frame 7/18/2025 Partial Inspection JOHN QUINTANILLA
BUILDING-Rough-Frame 7/24/2025 Approved BARRY HACHE
MERV13>=Rough 7/24/2025 Approved BARRY HACHE
Verify Sprinkler Sign Off 7/24/2025 Approved BARRY HACHE
Insulation 7/28/2025 Approved RONNIE MEDINA
Drywall Nailing 8/4/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 8/11/2025 No Access for Inspection RONNIE MEDINA
Interior/Exterior Lathing 8/13/2025 Approved RONNIE MEDINA