515-515 1/2 W 88TH ST 90044
Certificate Information: 515-515 1/2 W 88TH ST 90044
- Application / Permit
- 22010-10000-03850
- Plan Check / Job No.
- B22LA15222
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- *eplan* PROPOSED ADDITION AND CONVERSION OF (E) 1-STORY SFD TO A 2-STORY DUPLEX. *** BUILDING TO BE EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGHOUT*** 1 of 2
- Permit Issued
- Issued on 8/22/2024
- Issuing Office
- Current Status
- Issued on 8/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 9/18/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 9/20/2022 | GARO TELMI |
| Applicant returned to address corrections | 5/2/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 7/18/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 8/15/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 8/22/2024 | CRYSTEL MAALOUF |
| Plan Check Approved | 8/22/2024 | CRYSTEL MAALOUF |
| Issued | 8/22/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2023 | CELINA MORENO |
| Frnt yard landscape/Water mgmt | Cleared | 5/9/2023 | MAYELA VILLA |
| Hydrant and Access approval | Cleared | 5/19/2023 | LAVEON RIDER |
| Low Impact Development | Cleared | 9/28/2023 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2023 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 10/3/2023 | CELINA MORENO |
| Sewer availability | Cleared | 10/3/2023 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/25/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 9/25/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 9/25/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/27/2024 | Partial Inspection | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 10/16/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/16/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 11/12/2024 | Approved | JOSE MACIAS |
| Insulation | 11/15/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Partial Approval | JOHN QUINTANILLA |
| Wood Frame | 12/16/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Conditional Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2025 | Corrections Issued | JOHN QUINTANILLA |
| Deputy Wood Construction | 6/17/2025 | Conditional Approval | ANTHONY RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 7/8/2025 | Approved | RONNIE MEDINA |
| HVAC-Rough | 7/11/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 7/11/2025 | Approved | JOHN QUINTANILLA |
| Wood Frame | 7/11/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 7/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 7/18/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 7/18/2025 | Approved | JOHN QUINTANILLA |
| MERV13>=Rough | 7/18/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Wood Frame | 7/18/2025 | Partial Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | BARRY HACHE |
| MERV13>=Rough | 7/24/2025 | Approved | BARRY HACHE |
| Verify Sprinkler Sign Off | 7/24/2025 | Approved | BARRY HACHE |
| Insulation | 7/28/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 8/4/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 8/11/2025 | No Access for Inspection | RONNIE MEDINA |
| Interior/Exterior Lathing | 8/13/2025 | Approved | RONNIE MEDINA |