3878 N ENCINO HILLS PL 91436
Certificate Information: 3878 N ENCINO HILLS PL 91436
- Application / Permit
- 22010-10000-03844
- Plan Check / Job No.
- B22LA15209
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *eplan* new 1 story wingle family dwelling with an attached 2 car garage and an attached deck (bldg to be fire sprinklered (see comments)
- Permit Issued
- Issued on 5/16/2023
- Issuing Office
- Current Status
- CofO Issued on 2/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 8/2/2022 | APPLICANT |
Assigned to Plan Check Engineer | 8/11/2022 | MINA HABIB |
Corrections Issued | 8/31/2022 | MINA HABIB |
Quality Review Completed | 9/2/2022 | RODOLFO ARIAS |
Applicant returned to address corrections | 2/15/2023 | MINA HABIB |
Applicant returned to address corrections | 2/28/2023 | MINA HABIB |
Applicant returned to address corrections | 3/30/2023 | MINA HABIB |
Applicant returned to address corrections | 4/4/2023 | MINA HABIB |
Applicant returned to address corrections | 4/10/2023 | MINA HABIB |
Applicant returned to address corrections | 4/11/2023 | MINA HABIB |
Plan Check Approved | 5/11/2023 | MINA HABIB |
Issued | 5/16/2023 | APPLICANT |
CofO in Progress | 12/26/2024 | JEFFREY HARTLINE |
CofO in Progress | 12/26/2024 | JEFFREY HARTLINE |
CofO in Progress | 1/9/2025 | THOMAS FINNILA |
No Progress | 1/15/2025 | SEAN WIRCH |
CofO in Progress | 1/15/2025 | SEAN WIRCH |
Permit Finaled | 2/10/2025 | JOHN JANSON |
CofO Issued | 2/10/2025 | JOHN JANSON |
Permit Finaled | 2/10/2025 | JOHN JANSON |
Permit Application Clearance Information
Address approval | Cleared | 9/27/2022 | COLIN LOREDO |
BHO/Hillside ordinance | Cleared | 9/27/2022 | COLIN LOREDO |
BHO/Hillside ordinance | Cleared | 9/27/2022 | COLIN LOREDO |
BHO/Hillside ordinance | Cleared | 9/27/2022 | COLIN LOREDO |
BHO/Hillside ordinance | Cleared | 9/27/2022 | COLIN LOREDO |
BHO/Hillside ordinance | Cleared | 9/27/2022 | COLIN LOREDO |
Permit | Cleared | 9/27/2022 | COLIN LOREDO |
Eng Process Fee Ord 176,300 | Cleared | 9/28/2022 | COLIN LOREDO |
Sewer availability | Cleared | 9/28/2022 | COLIN LOREDO |
Certificate of Compliance | Cleared | 9/29/2022 | NELSON RODRIGUEZ |
Hydrant and Access approval | Cleared | 10/11/2022 | LAVEON RIDER |
Trees in Parkway | Cleared | 10/14/2022 | ADALBERTO VERA |
Low Impact Development | Cleared | 11/14/2022 | LUIS LUVANO |
Roof/Waste drainage to street | Cleared | 11/14/2022 | JOSE DUARTE-DIAZ |
Miscellaneous | Cleared | 1/11/2023 | NELSON RODRIGUEZ |
Certificate of Compliance | Cleared | 1/12/2023 | NELSON RODRIGUEZ |
Green Code | Cleared | 5/11/2023 | MINA HABIB |
Contact Information
Contractor | ; Lic. No.: 955109-B | , |
Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Geologist | Feffer,, Joshua R; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 5/19/2023 | Partial Inspection | JOHN KIDWELL |
Deputy Reinf. Concrete | 6/9/2023 | Approved | VINCENT HANLEY |
Piling/Pier/Caisson | 6/9/2023 | Not Ready for Inspection | VINCENT HANLEY |
Deputy Reinf. Concrete | 6/12/2023 | Approved | VINCENT HANLEY |
Deputy Reinf. Concrete | 6/13/2023 | Approved | VINCENT HANLEY |
Excavation/Setback/Form/Re-Bar | 6/13/2023 | Approved | VINCENT HANLEY |
Deputy Reinf. Concrete | 7/13/2023 | Approved | VINCENT HANLEY |
Footing/Foundation/Slab | 8/15/2023 | Corrections Issued | VINCENT HANLEY |
Deputy Other (see comments) | 8/31/2023 | Approved | VINCENT HANLEY |
Footing/Foundation/Slab | 8/31/2023 | Partial Approval | VINCENT HANLEY |
Deputy Other (see comments) | 9/5/2023 | Partial Approval | VINCENT HANLEY |
PLUMBING-Rough | 9/14/2023 | Approved | SEAN HAUPT |
Footing/Foundation/Slab | 9/29/2023 | Approved | VINCENT HANLEY |
BUILDING-Rough-Frame | 11/1/2023 | Partial Approval | VINCENT HANLEY |
Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Partial Approval | VINCENT HANLEY |
Green Building Rough | 11/1/2023 | Not Ready for Inspection | VINCENT HANLEY |
Verify Sprinkler Sign Off | 11/1/2023 | Not Ready for Inspection | VINCENT HANLEY |
Deputy Wood Construction | 11/15/2023 | Approved | VINCENT HANLEY |
Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Partial Approval | VINCENT HANLEY |
Green Building Rough | 11/15/2023 | Not Ready for Inspection | VINCENT HANLEY |
Verify Sprinkler Sign Off | 11/15/2023 | Not Ready for Inspection | VINCENT HANLEY |
ELECTRICAL-Rough | 12/26/2023 | Approved | VINCENT HANLEY |
HVAC-Rough | 12/28/2023 | Approved | VINCENT HANLEY |
PLUMBING-Rough | 1/3/2024 | Approved | VINCENT HANLEY |
Shower Pan | 1/3/2024 | Not Ready for Inspection | VINCENT HANLEY |
BUILDING-Rough-Frame | 1/4/2024 | Partial Approval | VINCENT HANLEY |
Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Approved | VINCENT HANLEY |
Green Building Rough | 1/4/2024 | Not Ready for Inspection | VINCENT HANLEY |
Verify Sprinkler Sign Off | 1/4/2024 | Not Ready for Inspection | VINCENT HANLEY |
Wood Frame | 1/4/2024 | Partial Approval | VINCENT HANLEY |
Shower Pan | 1/25/2024 | Approved | VINCENT HANLEY |
BUILDING-Rough-Frame | 2/9/2024 | Approved | VINCENT HANLEY |
Green Building Rough | 2/9/2024 | Approved | VINCENT HANLEY |
Interior/Exterior Lathing | 2/9/2024 | Approved | VINCENT HANLEY |
Verify Sprinkler Sign Off | 2/9/2024 | Approved | VINCENT HANLEY |
Insulation | 2/15/2024 | Corrections Issued | VINCENT HANLEY |
Drywall Nailing | 3/1/2024 | Approved | VINCENT HANLEY |
Pool Piping | 3/13/2024 | Approved | VINCENT HANLEY |
ELECTRICAL-Final | 5/14/2024 | Not Ready for Inspection | THOMAS FINNILA |
Service/Power Release | 5/14/2024 | Not Ready for Inspection | THOMAS FINNILA |
ELECTRICAL-Final | 8/16/2024 | Corrections Issued | THOMAS FINNILA |
ELECTRICAL-Final | 10/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
HVAC-Final | 10/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
Service/Power Release | 10/1/2024 | Not Ready for Inspection | THOMAS FINNILA |
Service/Power Release | 10/21/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
ELECTRICAL-Final | 10/28/2024 | Corrections Issued | THOMAS FINNILA |
Service/Power Release | 10/28/2024 | Not Ready for Inspection | THOMAS FINNILA |
ELECTRICAL-Final | 11/5/2024 | Approved | THOMAS FINNILA |
Final | 11/5/2024 | Not Ready for Inspection | THOMAS FINNILA |
HVAC-Final | 11/5/2024 | Corrections Issued | THOMAS FINNILA |
PLUMBING-Final | 11/5/2024 | Approved | THOMAS FINNILA |
HVAC-Final | 11/13/2024 | Approved | MORRIS JACKSON |
Service/Power Release | 11/19/2024 | Approved | SEAN WIRCH |
Final | 12/18/2024 | Corrections Issued | THOMAS FINNILA |
Green Building Final | 12/18/2024 | Approved | THOMAS FINNILA |
SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Approved | THOMAS FINNILA |
Smoke Detectors | 12/18/2024 | Approved | THOMAS FINNILA |
Final | 12/24/2024 | Partial Approval | JEFFREY HARTLINE |
Final | 12/26/2024 | Corrections Issued | JEFFREY HARTLINE |
Final | 1/8/2025 | OK to Issue CofO | THOMAS FINNILA |