661 S MORENO AVE 90049

Certificate Information: 661 S MORENO AVE 90049

Application / Permit
22010-10000-03822
Plan Check / Job No.
B22LA15075
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2-STORY SFD WITH BASEMENT AND ATTACHED 3-CAR GARAGE. 1 OF 6
Permit Issued
Issued on 10/12/2023
Issuing Office
Current Status
Issued on 10/12/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/5/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 MICHAEL LOPEZ
Corrections Issued 8/26/2022 MICHAEL LOPEZ
Quality Review Completed 8/31/2022 KEN GILL
Building Plans Picked Up 9/6/2022 APPLICANT
Applicant returned to address corrections 10/21/2022 TU HUA
Applicant returned to address corrections 2/14/2023 MICHAEL LOPEZ
Applicant returned to address corrections 7/10/2023 MICHAEL LOPEZ
Applicant returned to address corrections 7/26/2023 MICHAEL LOPEZ
Applicant returned to address corrections 10/4/2023 MICHAEL LOPEZ
Plan Check Approved 10/12/2023 MICHAEL LOPEZ
Issued 10/12/2023 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 9/15/2022 RYAN LY
Hydrant and Access approval Cleared 9/20/2022 LAVEON RIDER
Trees in Parkway Cleared 9/21/2022 ADALBERTO VERA
Permit Cleared 9/22/2022 AMAAN MALIK
Specific Plan Cleared 9/27/2022 FREDDY GARCIA
Eng Process Fee Ord 176,300 Cleared 10/14/2022 AMAAN MALIK
Sewer availability Cleared 10/14/2022 AMAAN MALIK
Low Impact Development Cleared 9/20/2023 ROGELIO CORTES
Excavation more than 5-ft deep Cleared 10/4/2023 CALOSHA APPROVED
Roof/Waste drainage to street Cleared 10/10/2023 ANTHONY MAINEZ

Contact Information

Contractor Abbott R T Construction Inc; Lic. No.: 746685-B 543 COUNTRY CLUB DRIVE BOX 205      SIMI VALLEY, CA 93065

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/18/2024 Partial Approval BEN MOLSTAD
Footing/Foundation/Slab 1/18/2024 Partial Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 2/28/2024 Partial Approval ASHLEY THOMPSON
Deputy Shotcrete 2/29/2024 Conditional Approval ASHLEY THOMPSON
Deputy Shotcrete 3/1/2024 Conditional Approval MICHAEL PELHAM
PLUMBING-Rough 3/21/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 3/27/2024 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 4/24/2024 Partial Approval OGANES TARAKHCHYAN
Pre-Inspection 5/14/2024 Partial Inspection KIRK SANDERS
Footing/Foundation/Slab 6/21/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 6/27/2024 Partial Approval KIRK SANDERS
Deputy Reinf. Concrete 7/1/2024 Conditional Approval KIRK SANDERS
PLUMBING-Rough 7/8/2024 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 7/30/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 8/8/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Conditional Approval KIRK SANDERS
PLUMBING-Rough 8/23/2024 Partial Approval ARAM AVEDISIAN
Sewer 9/5/2024 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Partial Approval JESUS RODRIGUEZ
Final 3/20/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/20/2025 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Conditional Approval KIRK SANDERS
Sewer 4/7/2025 Approved JAYLIN GRAVITTE
Excavation/Setback/Form/Re-Bar 5/12/2025 Not Ready for Inspection KIRK SANDERS
Special/Order Compliance 5/12/2025 Corrections Issued KIRK SANDERS
Underground Mechanical 5/12/2025 Partial Approval KIRK SANDERS
Rough-Elec/Plmb/HVAC 5/13/2025 Partial Approval KIRK SANDERS
Structural Steel Frame 5/13/2025 Partial Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 5/16/2025 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 5/19/2025 Conditional Approval KIRK SANDERS
HVAC-Rough 7/22/2025 Approved ARAM AVEDISIAN
Shower Pan 9/4/2025 Approved ARAM AVEDISIAN
Insulation 9/12/2025 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/23/2025 Partial Approval ARAM AVEDISIAN
Insulation 9/29/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 10/3/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 10/3/2025 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 10/8/2025 Partial Approval MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 10/27/2025 Partial Approval MICHAEL ALLEN
Masonry Wall/Backfill 10/27/2025 Partial Approval MICHAEL ALLEN
Interior/Exterior Lathing 11/3/2025 Approved MICHAEL ALLEN
Insulation 11/4/2025 Approved MICHAEL ALLEN
Drywall Nailing 11/24/2025 Approved MICHAEL ALLEN
Gas Test 5/28/2026 Partial Approval ANTHONY EGSON