661 S MORENO AVE 90049
Certificate Information: 661 S MORENO AVE 90049
- Application / Permit
- 22010-10000-03822
- Plan Check / Job No.
- B22LA15075
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 2-STORY SFD WITH BASEMENT AND ATTACHED 3-CAR GARAGE. 1 OF 6
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- Current Status
- Issued on 10/12/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | MICHAEL LOPEZ |
| Corrections Issued | 8/26/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 8/31/2022 | KEN GILL |
| Building Plans Picked Up | 9/6/2022 | APPLICANT |
| Applicant returned to address corrections | 10/21/2022 | TU HUA |
| Applicant returned to address corrections | 2/14/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/10/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/26/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/4/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 10/12/2023 | MICHAEL LOPEZ |
| Issued | 10/12/2023 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 9/15/2022 | RYAN LY |
| Hydrant and Access approval | Cleared | 9/20/2022 | LAVEON RIDER |
| Trees in Parkway | Cleared | 9/21/2022 | ADALBERTO VERA |
| Permit | Cleared | 9/22/2022 | AMAAN MALIK |
| Specific Plan | Cleared | 9/27/2022 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 10/14/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 9/20/2023 | ROGELIO CORTES |
| Excavation more than 5-ft deep | Cleared | 10/4/2023 | CALOSHA APPROVED |
| Roof/Waste drainage to street | Cleared | 10/10/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Abbott R T Construction Inc; Lic. No.: 746685-B | 543 COUNTRY CLUB DRIVE BOX 205 SIMI VALLEY, CA 93065 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 1/18/2024 | Partial Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 2/28/2024 | Partial Approval | ASHLEY THOMPSON |
| Deputy Shotcrete | 2/29/2024 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Shotcrete | 3/1/2024 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 3/21/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 3/27/2024 | Conditional Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/14/2024 | Partial Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 6/21/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 6/27/2024 | Partial Approval | KIRK SANDERS |
| Deputy Reinf. Concrete | 7/1/2024 | Conditional Approval | KIRK SANDERS |
| PLUMBING-Rough | 7/8/2024 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/30/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/8/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2024 | Conditional Approval | KIRK SANDERS |
| PLUMBING-Rough | 8/23/2024 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 9/5/2024 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Partial Approval | JESUS RODRIGUEZ |
| Final | 3/20/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 3/20/2025 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Conditional Approval | KIRK SANDERS |
| Sewer | 4/7/2025 | Approved | JAYLIN GRAVITTE |
| Excavation/Setback/Form/Re-Bar | 5/12/2025 | Not Ready for Inspection | KIRK SANDERS |
| Special/Order Compliance | 5/12/2025 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 5/12/2025 | Partial Approval | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 5/13/2025 | Partial Approval | KIRK SANDERS |
| Structural Steel Frame | 5/13/2025 | Partial Approval | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 5/16/2025 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 5/19/2025 | Conditional Approval | KIRK SANDERS |
| HVAC-Rough | 7/22/2025 | Approved | ARAM AVEDISIAN |
| Shower Pan | 9/4/2025 | Approved | ARAM AVEDISIAN |
| Insulation | 9/12/2025 | Conditional Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/23/2025 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 9/29/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/3/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/3/2025 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 10/8/2025 | Partial Approval | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 10/27/2025 | Partial Approval | MICHAEL ALLEN |
| Masonry Wall/Backfill | 10/27/2025 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/3/2025 | Approved | MICHAEL ALLEN |
| Insulation | 11/4/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 11/24/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 5/28/2026 | Partial Approval | ANTHONY EGSON |