113 1/4 W 105TH ST 90003
Certificate Information: 113 1/4 W 105TH ST 90003
- Application / Permit
- 22010-10000-03818
- Plan Check / Job No.
- B22LA15036
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New two detached ADUs per state 65852.2 e.1.D-LAMC 12.22 A.33 C-D ,G
- Permit Issued
- Issued on 4/28/2023
- Issuing Office
- Current Status
- Issued on 4/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | YASHAR EMAMI |
| Corrections Issued | 9/13/2022 | YASHAR EMAMI |
| Quality Review Completed | 9/27/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 1/23/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 3/1/2023 | YASHAR EMAMI |
| Plan Check Approved | 4/18/2023 | YASHAR EMAMI |
| Plan Check Approved | 4/27/2023 | YASHAR EMAMI |
| Issued | 4/28/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2022 | CINDY QI |
| Tenant Habitability Plan | Cleared | 10/27/2022 | MICHAEL SOTO |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2022 | CINDY QI |
| Low Impact Development | Cleared | 12/9/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 12/12/2022 | CINDY QI |
| Sewer availability | Cleared | 12/15/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 28025 DOROTHY DR STE 202 AGOURA HILLS, CA 91301 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 5/26/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Pre-Inspection | 5/26/2023 | Partial Inspection | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 5/31/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 5/31/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Underground Mechanical | 5/31/2023 | Approved | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 6/5/2023 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 6/5/2023 | Approved | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 6/15/2023 | Conditional Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/27/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Rough-Elec/Plmb/HVAC | 6/27/2023 | Corrections Issued | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 6/27/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 6/30/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Approved | JAMES CHAVEZ |
| Rough-Elec/Plmb/HVAC | 6/30/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 7/3/2023 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 7/6/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 7/6/2023 | Approved | JAMES CHAVEZ |
| Gas Test | 7/11/2023 | Approved | JAMES CHAVEZ |
| Insulation | 7/11/2023 | Approved | JAMES CHAVEZ |
| Sewer | 7/11/2023 | Approved | JAMES CHAVEZ |
| Shower Pan | 7/11/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 7/17/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 7/17/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 10/10/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 10/10/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 10/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 10/15/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Pre-Inspection | 1/8/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 2/27/2026 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Not Required | JOSEPH MCGARRY |
| Service/Power Release | 2/27/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 2/27/2026 | Approved | JOSEPH MCGARRY |
| Final | 3/9/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Service/Power Release | 3/9/2026 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 3/16/2026 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 3/16/2026 | Not Ready for Inspection | BEN MOLSTAD |