368 3/4 N AVENUE 53 90042

Certificate Information: 368 3/4 N AVENUE 53 90042

Application / Permit
22010-10000-03815
Plan Check / Job No.
B22LA15035
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New 2-story 1200 s.f. ADU PER ORDINANCE
Permit Issued
Issued on 1/9/2024
Issuing Office
Current Status
CofO Issued on 3/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/25/2022 JAD BASMA
Corrections Issued 9/1/2022 JAD BASMA
Quality Review Completed 9/8/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 12/1/2023 JAD BASMA
Plan Check Approved 1/4/2024 JAD BASMA
Issued 1/9/2024 APPLICANT
CofO in Progress 3/13/2025 NICHOLAS LOPEZ
Permit Finaled 3/16/2025 DEROLD HAUFF
CofO Issued 3/16/2025 DEROLD HAUFF
Permit Finaled 3/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 3/22/2023 CELINA MORENO
Address approval Cleared 6/15/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/15/2023 CELINA MORENO
Sewer availability Cleared 6/15/2023 CELINA MORENO
Trees in Parkway Cleared 7/8/2023 ADALBERTO VERA
HPOZ Cleared 8/14/2023 MICAELA TORRES-GIL
Low Impact Development Cleared 8/24/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 9/8/2023 NEIL TUANO
GPI Written Notices Cleared 1/4/2024 JAD BASMA
Grading Pre-Inspection Cleared 1/4/2024 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/3/2024 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/4/2024 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/8/2024 Approved HAMIK HARTOUNIAN
Grounding or Bonding 4/8/2024 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/16/2024 Partial Approval JEFFREY MEAD
PLUMBING-Rough 4/18/2024 Partial Approval BRIAN SULLIVAN
Sewer 4/18/2024 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Corrections Issued JEFFREY MEAD
Wood Frame 4/22/2024 Not Ready for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 5/17/2024 No Access for Inspection THOMAS LOGRASSO
PLUMBING-Rough 5/20/2024 Approved THOMAS LOGRASSO
Special/Order Compliance 5/20/2024 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 5/23/2024 Approved BRENDAN MORELLI
Deputy Wood Construction 5/31/2024 Conditional Approval THOMAS LOGRASSO
Underground Mechanical 6/6/2024 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 6/11/2024 Partial Approval THOMAS LOGRASSO
HVAC-Rough 6/11/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 8/2/2024 Approved THOMAS LOGRASSO
Sewer 8/15/2024 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 8/16/2024 Corrections Issued THOMAS LOGRASSO
Shower Pan 8/16/2024 Approved THOMAS LOGRASSO
Shower Pan 8/19/2024 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 8/19/2024 Partial Inspection ALEX COLIN
Interior/Exterior Lathing 8/20/2024 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 8/27/2024 Not Ready for Inspection THOMAS LOGRASSO
Insulation 9/6/2024 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 9/18/2024 Partial Approval THOMAS LOGRASSO
Drywall Nailing 9/25/2024 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 10/21/2024 Approved THOMAS LOGRASSO
Drywall Nailing 10/21/2024 Approved THOMAS LOGRASSO
Insulation 10/21/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 10/21/2024 Approved THOMAS LOGRASSO
Sewer 11/13/2024 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Final 11/19/2024 Partial Inspection THOMAS LOGRASSO
Sewer 11/19/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 11/26/2024 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Final 12/13/2024 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Final 12/13/2024 Approved THOMAS LOGRASSO
PLUMBING-Final 12/13/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 12/26/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 12/26/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/26/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 12/26/2024 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 12/26/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 12/26/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 1/17/2025 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 3/3/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 3/3/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 3/6/2025 Approved NICHOLAS LOPEZ
Final 3/6/2025 Corrections Issued NICHOLAS LOPEZ
HVAC-Final 3/6/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 3/6/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/6/2025 SGSOV No Gas NICHOLAS LOPEZ
Service/Power Release 3/6/2025 Not Required NICHOLAS LOPEZ
Smoke Detectors 3/6/2025 Approved NICHOLAS LOPEZ
Final 3/11/2025 Partial Approval NICHOLAS LOPEZ
Service/Power Release 3/11/2025 Approved NICHOLAS LOPEZ
Final 3/13/2025 OK to Issue CofO NICHOLAS LOPEZ