544 N MANSFIELD AVE 90036

Certificate Information: 544 N MANSFIELD AVE 90036

Application / Permit
22010-10000-03803
Plan Check / Job No.
B22LA14993
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert 21'X21' detached garage to an ADU include existing second floor Rec. room over proposed garage to an ADU
Permit Issued
Issued on 9/1/2022
Issuing Office
Current Status
CofO Issued on 1/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2022 APPLICANT
Assigned to Plan Check Engineer 8/5/2022 JOE VO
Corrections Issued 8/7/2022 JOE VO
Plan Check Approved 8/29/2022 JOE VO
Issued 9/1/2022 APPLICANT
CofO in Progress 1/12/2023 JOAQUIN GREENOUGH
Permit Finaled 1/14/2023 DEROLD HAUFF
CofO Issued 1/14/2023 DEROLD HAUFF
Permit Finaled 1/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/29/2022 TREVOR QUAN
Sewer availability Cleared 8/29/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/30/2022 TREVOR QUAN

Contact Information

Contractor A U D Construction Inc; Lic. No.: 794151-B       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2022 Corrections Issued JOAQUIN GREENOUGH
Pre-Inspection 9/9/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/15/2022 Approved JOAQUIN GREENOUGH
Pre-Inspection 9/15/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 11/28/2022 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/6/2022 Corrections Issued JOAQUIN GREENOUGH
HVAC-Rough 12/6/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 12/6/2022 Corrections Issued JOAQUIN GREENOUGH
Gas Test 12/28/2022 Partial Approval JOSEPH MCGARRY
Underground Mechanical 12/28/2022 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 1/4/2023 Approved JOAQUIN GREENOUGH
Final 1/4/2023 Corrections Issued JOAQUIN GREENOUGH
METHANE-Final 1/4/2023 Approved JOAQUIN GREENOUGH
METHANE-Rough 1/4/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 1/4/2023 Approved JOAQUIN GREENOUGH
Final 1/5/2023 Corrections Issued JOAQUIN GREENOUGH
Final 1/11/2023 OK to Issue CofO JOAQUIN GREENOUGH