930-932 1/2 E IMPERIAL HWY 90059
Certificate Information: 930-932 1/2 E IMPERIAL HWY 90059
- Application / Permit
- 22010-10000-03772
- Plan Check / Job No.
- B22LA14866
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE 2 STORY SFD WITH ATTACHED ADU ADU PER GCS 65852.2(e)(1)(A) FOR NEW SFD
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2022 | ADRIANA LOPEZ |
| Corrections Issued | 10/27/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 11/10/2022 | KEN GILL |
| Building Plans Picked Up | 11/16/2022 | APPLICANT |
| Plan Check Approved | 4/28/2023 | ADRIANA LOPEZ |
| Issued | 5/5/2023 | APPLICANT |
| CofO in Progress | 3/27/2024 | ANSON MAGLASANG |
| Permit Finaled | 3/27/2024 | ANSON MAGLASANG |
| CofO Issued | 3/27/2024 | ANSON MAGLASANG |
| Permit Finaled | 3/27/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 12/8/2022 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2023 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 2/1/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/1/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 2/1/2023 | ADRIAN SANCHEZ |
| Community Plan Implem. Overlay | Cleared | 2/13/2023 | HELEN JADALI |
| Hydrant and Access approval | Cleared | 2/21/2023 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/10/2023 | Not Ready for Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 7/12/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/12/2023 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 7/18/2023 | Partial Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Approved | JOHN KLARIN |
| Sewer | 9/5/2023 | Approved | JOHN KLARIN |
| Insulation | 10/6/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 10/16/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 10/16/2023 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 10/30/2023 | Approved | JOHN KLARIN |
| Wood Frame | 10/30/2023 | Approved | JOHN KLARIN |
| Gas Test | 11/28/2023 | Approved | JOHN KLARIN |
| Underground Mechanical | 11/28/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 2/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 2/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Final | 2/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| MERV13>=Final | 2/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| MERV13>=Rough | 2/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 2/8/2024 | SGSOV Approved | ANSON MAGLASANG |
| Service/Power Release | 2/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Smoke Detectors | 2/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Verify Sprinkler Sign Off | 2/8/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 3/8/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 3/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 3/8/2024 | Approved | BEN MOLSTAD |
| Green Building Final | 3/8/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 3/8/2024 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Final | 3/8/2024 | Approved | BEN MOLSTAD |
| MERV13>=Rough | 3/8/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 3/8/2024 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 3/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 3/8/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 3/8/2024 | Approved | BEN MOLSTAD |
| Final | 3/14/2024 | Corrections Issued | BEN MOLSTAD |
| Service/Power Release | 3/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 3/19/2024 | OK to Issue CofO | ANSON MAGLASANG |
| Service/Power Release | 3/19/2024 | Approved | ANSON MAGLASANG |