624 W 51ST ST 90037

Certificate Information: 624 W 51ST ST 90037

Application / Permit
22010-10000-03764
Plan Check / Job No.
B22VN10100
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan NEW 2-STORY S.F.D. W/ ATTACHED 2 CAR GARAGE (REAR)
Permit Issued
Issued on 5/22/2023
Issuing Office
Current Status
CofO Issued on 11/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 ADRIANA LOPEZ
Corrections Issued 7/24/2022 ADRIANA LOPEZ
Quality Review Completed 7/29/2022 FARUK SEZER
Applicant returned to address corrections 12/27/2022 ADRIANA LOPEZ
Applicant returned to address corrections 2/8/2023 ADRIANA LOPEZ
Plan Check Approved 2/24/2023 ADRIANA LOPEZ
Issued 5/22/2023 APPLICANT
CofO in Progress 11/17/2023 ALEJANDRO DE ARTOLA
Permit Finaled 11/26/2023 DEROLD HAUFF
CofO Issued 11/26/2023 DEROLD HAUFF
Permit Finaled 11/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/24/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/25/2022 STEVE MELGAR
Sewer availability Cleared 8/25/2022 STEVE MELGAR
Low Impact Development Cleared 9/21/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 9/27/2022 STEVE MELGAR
Hydrant and Access approval Cleared 10/3/2022 MATTHEW CRAIG
Highway dedication Cleared 10/17/2022 STEVE MELGAR

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/7/2023 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 6/12/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Partial Approval ALEJANDRO DE ARTOLA
Special/Order Compliance 7/26/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 8/10/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 8/10/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 8/11/2023 Approved BRENDAN MORELLI
ELECTRICAL-Rough 8/11/2023 Approved BRENDAN MORELLI
Green Building Rough 8/11/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 8/11/2023 Partial Approval BRENDAN MORELLI
Verify Sprinkler Sign Off 8/11/2023 Approved BRENDAN MORELLI
Insulation 8/14/2023 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 8/24/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/24/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/25/2023 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/28/2023 Approved ALEJANDRO DE ARTOLA
Sewer 9/20/2023 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 9/20/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 10/6/2023 Corrections Issued DAVID FEILER
ELECTRICAL-Final 10/7/2023 Corrections Issued DAVID FEILER
ELECTRICAL-Final 10/11/2023 Approved CRAIG DAVIS
ELECTRICAL-Final 11/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 11/15/2023 Approved ALEJANDRO DE ARTOLA
Green Building Final 11/15/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/15/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/15/2023 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/15/2023 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 11/15/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/16/2023 Approved ALEJANDRO DE ARTOLA
Final 11/16/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Gas Test 11/16/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/16/2023 Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/16/2023 Approved ALEJANDRO DE ARTOLA