4856 W 4TH ST 90020
Certificate Information: 4856 W 4TH ST 90020
- Application / Permit
- 22010-10000-03756
- Plan Check / Job No.
- B22LA14823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: New 2nd Story ADU over existing Garage/Rec room. See Comment.
- Permit Issued
- Issued on 4/10/2023
- Issuing Office
- Current Status
- CofO Corrected on 12/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | TSE MING HUANG |
| Corrections Issued | 8/15/2022 | TSE MING HUANG |
| Quality Review Completed | 8/24/2022 | EUGENE BARBEAU |
| Plan Check Approved | 3/24/2023 | TSE MING HUANG |
| Issued | 4/10/2023 | APPLICANT |
| CofO in Progress | 11/4/2024 | RONNIE MINDANAO |
| Permit Finaled-Status Void | 11/10/2024 | DEROLD HAUFF |
| CofO Issued-Status Void | 11/10/2024 | DEROLD HAUFF |
| Re-Activate Permit | 12/18/2024 | DEROLD HAUFF |
| Permit Finaled | 12/18/2024 | DEROLD HAUFF |
| CofO Corrected | 12/18/2024 | DEROLD HAUFF |
| Permit Finaled | 12/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 9/6/2022 | JEANETTE VONG |
| CPC | Cleared | 10/24/2022 | DAMIAN GATTO |
| CPC | Cleared | 10/24/2022 | DAMIAN GATTO |
| CPC | Cleared | 10/24/2022 | DAMIAN GATTO |
| HPOZ | Cleared | 10/24/2022 | DAMIAN GATTO |
| Miscellaneous | Cleared | 10/24/2022 | DAMIAN GATTO |
| ZI | Cleared | 10/24/2022 | DAMIAN GATTO |
| Low Impact Development | Cleared | 11/23/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | TREVOR QUAN |
Contact Information
| Contractor | Lab 310; Lic. No.: 711587-B | , |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/12/2023 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 5/16/2023 | Partial Approval | LILIANA PORTILLO |
| METHANE-Barrier | 5/16/2023 | Approved | LILIANA PORTILLO |
| METHANE-Subgrade | 5/16/2023 | Approved | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 5/24/2023 | Conditional Approval | RICHARD DOCKUS |
| Deputy Reinf. Concrete | 5/24/2023 | Conditional Approval | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 5/24/2023 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 6/2/2023 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 8/2/2023 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 10/4/2023 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 11/17/2023 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 12/1/2023 | Approved | RICHARD DOCKUS |
| Insulation | 12/1/2023 | Corrections Issued | RICHARD DOCKUS |
| Shower Pan | 12/1/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 1/9/2024 | Partial Approval | RICHARD DOCKUS |
| Interior/Exterior Lathing | 2/27/2024 | Corrections Issued | RICHARD DOCKUS |
| Interior/Exterior Lathing | 3/8/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 3/21/2024 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 7/30/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 7/30/2024 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 7/30/2024 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 7/30/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 7/30/2024 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 8/16/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 8/16/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 8/16/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Final | 8/16/2024 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Final | 8/16/2024 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 8/16/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 8/16/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Service/Power Release | 8/16/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 8/16/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 8/27/2024 | Approved | RONNIE MINDANAO |
| Final | 8/27/2024 | Conditional Approval | RONNIE MINDANAO |
| HVAC-Final | 8/27/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 8/27/2024 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/27/2024 | SGSOV Approved | RONNIE MINDANAO |
| Final | 11/4/2024 | OK to Issue CofO | RONNIE MINDANAO |